Permit: TR-ROW-0424-00450
Permit Details
Apply Date:
04/23/2024
Applicant:
Caitlin Ripley
Description:
(CONTINUATION OF WORK FROM Expired permit TR-ROW-1123-01371) --- ROW Utilities Scope of work along 15th Ave and Alturas Street - Extend for 12 additional weeks for civil work to include underground utilities and driveway to housing development along Alturas Street and 15th Avenue. Permit update 8/7/2024: Paving has been delayed due to Sewer and TEP Work Inspections. Requesting a 60 day extension allowing for all underground utilities to be inspected and moratorium paving work to be completed.
Permit Reviews
Permit Number - TR-ROW-0424-00450
Permit Status: Issued
Permit Description: (CONTINUATION OF WORK FROM Expired permit TR-ROW-1123-01371) --- ROW Utilities Scope of work along 15th Ave and Alturas Street - Extend for 12 additional weeks for civil work to include underground utilities and driveway to housing development along Alturas Street and 15th Avenue.
Permit update 8/7/2024: Paving has been delayed due to Sewer and TEP Work Inspections. Requesting a 60 day extension allowing for all underground utilities to be inspected and moratorium paving work to be completed.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/23/2024 | RIGHT-OF-WAY REVIEW v.1 | 04/24/2024 | REQUIRES RESUBMIT |
10/03/2024 | RIGHT-OF-WAY REVIEW v.1 | 10/04/2024 | REQUIRES RESUBMIT |
05/02/2024 | RIGHT-OF-WAY REVIEW v.2 | 05/03/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0424-00450
Permit Status: Issued
Permit Description: (CONTINUATION OF WORK FROM Expired permit TR-ROW-1123-01371) --- ROW Utilities Scope of work along 15th Ave and Alturas Street - Extend for 12 additional weeks for civil work to include underground utilities and driveway to housing development along Alturas Street and 15th Avenue.
Permit update 8/7/2024: Paving has been delayed due to Sewer and TEP Work Inspections. Requesting a 60 day extension allowing for all underground utilities to be inspected and moratorium paving work to be completed.
Total Outstanding Activity Conditions - 4
Date | Name |
---|---|
04/24/2024 | Traffic Control set-up approved between 7AM - 5PM |
04/24/2024 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
04/24/2024 | Pavement Patch type Shall Be in conformance to the current edition of the City of Tucson Public Utility Administrative Manual. |
04/24/2024 | Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 |
Outstanding Inspections
Permit Status: Issued
Permit Number: TR-ROW-0424-00450
Permite Description: (CONTINUATION OF WORK FROM Expired permit TR-ROW-1123-01371) --- ROW Utilities Scope of work along 15th Ave and Alturas Street - Extend for 12 additional weeks for civil work to include underground utilities and driveway to housing development along Alturas Street and 15th Avenue.
Permit update 8/7/2024: Paving has been delayed due to Sewer and TEP Work Inspections. Requesting a 60 day extension allowing for all underground utilities to be inspected and moratorium paving work to be completed.
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/23/2024 | TRSP - ROW - Final/Close-Out | N/A | Re-inspection required |
Completed Inspections
Permit Status: Issued
Permit Number: TR-ROW-0424-00450
Permit Description: (CONTINUATION OF WORK FROM Expired permit TR-ROW-1123-01371) --- ROW Utilities Scope of work along 15th Ave and Alturas Street - Extend for 12 additional weeks for civil work to include underground utilities and driveway to housing development along Alturas Street and 15th Avenue.
Permit update 8/7/2024: Paving has been delayed due to Sewer and TEP Work Inspections. Requesting a 60 day extension allowing for all underground utilities to be inspected and moratorium paving work to be completed.
Total Completed Inspections - 8
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/21/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
08/06/2024 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
08/06/2024 | TRSP - ROW - Paving - Subgrade/removal/placement | Passed | ||
08/07/2024 | TRSP - ROW - Barricade Takedown | Passed | ||
08/07/2024 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
08/09/2024 | TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) | Passed | ||
09/19/2024 | TRSP - ROW - Concrete - Acceptance (Post-Pour) | Passed | ||
10/03/2024 | TRSP - ROW - Final/Close-Out | Passed |