Permit: TR-ROW-0326-00344
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW)
Address:
Unknown
Address NEW:
Unknown
Apply Date:
03/24/2026
Applicant:
Alexis Otero-Morales
Description:
Water line removals. 3/ 5’W X 5’L X 7’D excavations in the asphalt to abandon water lines.***
Permit Reviews
Permit Number - TR-ROW-0326-00344
Permit Status: Complete
Permit Description: Water line removals. 3/ 5’W X 5’L X 7’D excavations in the asphalt to abandon water lines.***
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/23/2026 | RIGHT-OF-WAY REVIEW v.2 | 04/29/2026 | REQUIRES RESUBMIT |
| 03/24/2026 | RIGHT-OF-WAY REVIEW v.1 | 04/22/2026 | REQUIRES RESUBMIT |
| 05/01/2026 | RIGHT-OF-WAY REVIEW v.3 | 05/01/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0326-00344
Permit Status: Complete
Permit Description: Water line removals. 3/ 5’W X 5’L X 7’D excavations in the asphalt to abandon water lines.***
Total Outstanding Activity Conditions - 8
| Date | Name |
|---|---|
| 05/01/2026 | The following extended traffic control set-up times were approved: Night Work Permit with TNE |
| 05/01/2026 | - The contractor shall restore all disturbed pavement in accordance with the City of Tucson Standard Specifications for Public Improvements and applicable standard details. All pavement patches shall match the existing pavement section and surface condition. The contractor shall maintain all temporary patches in a safe and drivable condition until permanent restoration is completed. Any settlement, cracking, or pavement failure within the patched area shall be repaired by the contractor at no cost to the City for the duration of the warranty period |
| 05/01/2026 | All excavations must be securely plated or backfilled at the end of each workday and during any period when the site is unattended. Plating shall be traffic-rated, flush with the surrounding surface, and properly secured to prevent movement and to maintain public safety |
| 05/01/2026 | Approved Temporary Noise Exemption required prior to Night work being performed within the City of Tucson Right of Way.. |
| 05/01/2026 | BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION WITH jose.garcia@tucsonaz.gov.. Due to the presence of a bus stop in the area, the contractor is required to contact Joe Garcia, Sun Tran Dispatch, at 520-576-8726 no less than 48 business hours before beginning work to coordinate impacts. |
| 05/01/2026 | Lane closures shall only be permitted during active work operations. At the end of each workday, the contractor shall remove all traffic control devices and reopen the roadway, bike lanes, and sidewalks to normal operation. Twenty-four (24) hour lane closures are not permitted unless specifically approved by the City. Traffic Control Devices shall not be stored in the bike lane or sidewalk |
| 05/01/2026 | Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14 Bike Lane Access and Accommodation 1) Posted Speeds 30 Mph or Less – Less than 14 lane - Use of the R4-11 alone is acceptable and preferred over Share The Road sign - 2) Posted Speeds 30 Mph or less – greater than 14 lane - Use of Share The Road sign is preferred 3) Posted Speeds 30 Mph or More – Any Lane Size - Provide a reasonable alternative for cyclists, such as a paved path, space behind barricades, or bike detour. Acceptable to direct cyclists to the sidewalk when properly signed depending on conditions 4) Bike lane to be maintained within Traffic Control closure and Share may Pedestrian detour path with proper R9-6 Sign. |
| 05/01/2026 | Pre-Activity Meeting w/Inspections Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0326-00344
Permit Description: Water line removals. 3/ 5’W X 5’L X 7’D excavations in the asphalt to abandon water lines.***
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/18/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | Tucson water inspector on site Amanda Head 520-343-5235. AWP Safty Brian Williams traffic control protector 520-360-9403 he moved the traffic control back for a bigger buffer at park he wanted to give the contractors at least five skips at the park intersection east of park in the westbound lane park this was his decision for safety of the contractor I documented this and left his contact information if there was any questions. The contractor did not have a problem with this. | |
| 05/18/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 05/21/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed | starting at 6 PM tomorrow they will be finishing clearing the rest of the holes so they can get the shoring in there get the clamps on over the abandonment. They have to cut out a little bit more asphalt of the whole closest to Euclid shut down time is 10 o’clock they have a backfill compaction test listed for 2 AM tomorrow night or Thursday morning. They plan on doing the asphalt on Thursday morning at 5 AM. 5/21/2026 Abandonment, they will be coming back and doing a Millin fill later on down the project for this area and the surrounding new building | |
| 05/22/2026 | TRSP - ROW - Final | Passed | Permanent hot patches have been put in place, but they were gonna have to mill and fill each lane because of multiple cuts and get another permit passing this permit |