Permit: TR-ROW-0326-00327
Permit Details
Status:
Needs Resubmittal
Type:
Right-of-Way (ROW)
Address:
720 W PRINCE RD
Address NEW:
720 W PRINCE RD
Apply Date:
03/19/2026
Applicant:
Marvin Murphy
Description:
Remove and replace existing channel with new PAG scupper, sidewalk and ramp 04/01/26-- Revision TCP with 24 hours.
Permit Reviews
Permit Number - TR-ROW-0326-00327
Permit Status: Needs resubmittal
Permit Description: Remove and replace existing channel with new PAG scupper, sidewalk and ramp
04/01/26-- Revision TCP with 24 hours.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/26/2026 | RIGHT-OF-WAY REVIEW REVISION v.1 | 04/03/2026 | REQUIRES RESUBMIT |
| 03/20/2026 | RIGHT-OF-WAY REVIEW v.1 | 03/24/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0326-00327
Permit Status: Needs resubmittal
Permit Description: Remove and replace existing channel with new PAG scupper, sidewalk and ramp
04/01/26-- Revision TCP with 24 hours.
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 03/24/2026 | ADA Detour Route required- Pedestrian to be maintained on existing side of ROW. Distance to nearest Signalized Marked crossing exceeds permitted length --Bikes to be Maintained within TC Closure |
| 03/24/2026 | Bus stop in the area, contact Joe Garcia, Sun Tran Dispatch, at 520-576-8726 at least 48-business hours prior to start of work for coordination. |
| 03/24/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 03/24/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 03/24/2026 | Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14 Bike Lane Access and Accommodation 1) Posted Speeds 30 Mph or Less – Less than 14 lane - Use of the R4-11 alone is acceptable and preferred over Share The Road sign - 2) Posted Speeds 30 Mph or less – greater than 14 lane - Use of Share The Road sign is preferred 3) Posted Speeds 30 Mph or More – Any Lane Size - Provide a reasonable alternative for cyclists, such as a paved path, space behind barricades, or bike detour. Acceptable to direct cyclists to the sidewalk when properly signed depending on conditions 4) Bike lane to be maintained within Traffic Control closure and Share may Pedestrian detour path with proper R9-6 Sign. |
Completed Inspections
Permit Status: Needs Resubmittal
Permit Number: TR-ROW-0326-00327
Permit Description: Remove and replace existing channel with new PAG scupper, sidewalk and ramp
04/01/26-- Revision TCP with 24 hours.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/26/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 04/03/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 04/03/2026 | TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) | Passed | ||
| 04/03/2026 | TRSP - ROW - Concrete - Acceptance (Post-Pour) | Passed |