Permit: TR-ROW-0326-00270
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW)
Address:
4726 S APPLE TREE AV
Address NEW:
4726 S APPLE TREE AV
Apply Date:
03/09/2026
Applicant:
Jose Tapia
Description:
Sidewalk repair with notice of violation. sidewalk 1 panel are 4x4
Permit Reviews
Permit Number - TR-ROW-0326-00270
Permit Status: Complete
Permit Description: Sidewalk repair with notice of violation. sidewalk 1 panel are 4x4
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/09/2026 | RIGHT-OF-WAY REVIEW v.1 | 03/09/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0326-00270
Permit Status: Complete
Permit Description: Sidewalk repair with notice of violation. sidewalk 1 panel are 4x4
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 03/09/2026 | Traffic Control set-up approved between 7AM - 5PM |
| 03/09/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 03/09/2026 | PER MUTCD PROPER ADVANCED WARNING SIGNS AHEAD ARE REQUIRED. PEDESTRAIN ACCESS MUST BE PROVIDED AND MAINTAINED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. REPLACE/REPAIR SIDEWALKS PANELS PER PAG STANDARD DETAIL 200/206 |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0326-00270
Permit Description: Sidewalk repair with notice of violation. sidewalk 1 panel are 4x4
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/11/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | Contractor notified of all specs and requirements. | |
| 04/01/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | TCP set up per permit | |
| 04/01/2026 | TRSP - ROW - Final | Passed | area has been restored to original or better | |
| 04/01/2026 | TRSP - ROW - Concrete - Acceptance (Post-Pour) | Passed | New panels in good condition and meet specifications and standards. | |
| 04/01/2026 | TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) | Passed | area ready for pour |