Permit: TR-ROW-0325-00297
Permit Details
Apply Date:
03/03/2025
Applicant:
ANGEL MORALES
Description:
Please submit. Trench 4’W X 4’D X4’L for mew sewer tie in on Main.***
Permit Reviews
Permit Number - TR-ROW-0325-00297
Permit Status: Complete
Permit Description: Please submit. Trench 4’W X 4’D X4’L for mew sewer tie in on Main.***
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/05/2025 | RIGHT-OF-WAY REVIEW v.1 | 03/10/2025 | REQUIRES RESUBMIT |
| 03/18/2025 | RIGHT-OF-WAY REVIEW v.2 | 03/19/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0325-00297
Permit Status: Complete
Permit Description: Please submit. Trench 4’W X 4’D X4’L for mew sewer tie in on Main.***
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 03/07/2025 | Traffic control set-up approved between 9AM - 3:30PM |
| 03/07/2025 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 03/07/2025 | BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TR-ROW-0325-00297
Permite Description: Please submit. Trench 4’W X 4’D X4’L for mew sewer tie in on Main.***
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/16/2025 | TRSP - ROW - Paving - Subgrade/removal/placement | N/A | Re-inspection required |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0325-00297
Permit Description: Please submit. Trench 4’W X 4’D X4’L for mew sewer tie in on Main.***
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/22/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 06/18/2025 | TRSP - ROW - Barricade Takedown | Passed | ||
| 06/27/2025 | TRSP - ROW - Final | Passed | ||
| 05/29/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 07/31/2025 | TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) | Passed | ||
| 10/08/2025 | TRSP - ROW - Paving - Subgrade/removal/placement | Passed |