Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Right-of-Way (ROW)
Address NEW:
533 W SPEEDWAY BL
Apply Date:
03/08/2024
Applicant:
Cameron Bonner
Description:
323058 Site 3 - (continuation of permit TR-ROW-0324-00271) Install Approximately 270 LF of 8" Cured in Place Pipe. The Cured in Place Pipe is a trench-less technology for sewer rehabilitation and does NOT require disturbance of the earth. Bench rehab and concrete collar will be completed on MH 9859-19 per PCRWRD standard detail 212.

Permit Reviews

Permit Number - TR-ROW-0324-00272
Permit Status: Complete
Permit Description: 323058 Site 3 - (continuation of permit TR-ROW-0324-00271) Install Approximately 270 LF of 8" Cured in Place Pipe. The Cured in Place Pipe is a trench-less technology for sewer rehabilitation and does NOT require disturbance of the earth. Bench rehab and concrete collar will be completed on MH 9859-19 per PCRWRD standard detail 212.
Start Date Submittal Complete Date Status  
03/11/2024 RIGHT-OF-WAY REVIEW v.1 03/15/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-0324-00272
Permit Status: Complete
Permit Description: 323058 Site 3 - (continuation of permit TR-ROW-0324-00271) Install Approximately 270 LF of 8" Cured in Place Pipe. The Cured in Place Pipe is a trench-less technology for sewer rehabilitation and does NOT require disturbance of the earth. Bench rehab and concrete collar will be completed on MH 9859-19 per PCRWRD standard detail 212.
Total Outstanding Activity Conditions - 2
Date Name
03/12/2024 Bus stop/ route
03/12/2024 Traffic control set-up approved between 9AM - 3:30PM

Completed Inspections

Permit Status: Complete
Permit Number: TR-ROW-0324-00272
Permit Description: 323058 Site 3 - (continuation of permit TR-ROW-0324-00271) Install Approximately 270 LF of 8" Cured in Place Pipe. The Cured in Place Pipe is a trench-less technology for sewer rehabilitation and does NOT require disturbance of the earth. Bench rehab and concrete collar will be completed on MH 9859-19 per PCRWRD standard detail 212.
Total Completed Inspections - 3
Date Description Inspector Results Comments
06/18/2024 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
06/18/2024 TRSP - ROW - Backfill - Placement/Compaction Passed
06/18/2024 TRSP - ROW - Notice of Completion Passed

Documents

File Name Document Type  
COT - TR - ROW PERMIT.PDF DOCUMENTS VIEW
323058 - SITE 3 FMP MAP (533 W SPEEDWAY BLVD) - 1_V1.PDF DOCUMENTS VIEW
DB 68897 - PAGE 3 - 533 W SPEEDWAY BLVD - BUMPOUTS - 3230XX6_V1.PDF DOCUMENTS VIEW