Permit: TR-ROW-0324-00271
Permit Details
Apply Date:
03/08/2024
Applicant:
Cameron Bonner
Description:
323058 Site 2 - Install Approximately 252 LF of 10" Cured in Place Pipe. The Cured in Place Pipe is a trench-less technology for sewer rehabilitation and does NOT require disturbance of the earth. Bench rehab's and new concrete collars will be completed on MH's 9855-06 and MH 9855-04 per PCRWRD standard detail 211.
Permit Reviews
Permit Number - TR-ROW-0324-00271
Permit Status: Complete
Permit Description: 323058 Site 2 - Install Approximately 252 LF of 10" Cured in Place Pipe. The Cured in Place Pipe is a trench-less technology for sewer rehabilitation and does NOT require disturbance of the earth. Bench rehab's and new concrete collars will be completed on MH's 9855-06 and MH 9855-04 per PCRWRD standard detail 211.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/11/2024 | RIGHT-OF-WAY REVIEW v.1 | 03/15/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0324-00271
Permit Status: Complete
Permit Description: 323058 Site 2 - Install Approximately 252 LF of 10" Cured in Place Pipe. The Cured in Place Pipe is a trench-less technology for sewer rehabilitation and does NOT require disturbance of the earth. Bench rehab's and new concrete collars will be completed on MH's 9855-06 and MH 9855-04 per PCRWRD standard detail 211.
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 03/12/2024 | Bus stop/ route |
| 03/12/2024 | Multiple Jurisdictions |
| 03/12/2024 | Traffic control set-up approved between 9AM - 3:30PM |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0324-00271
Permit Description: 323058 Site 2 - Install Approximately 252 LF of 10" Cured in Place Pipe. The Cured in Place Pipe is a trench-less technology for sewer rehabilitation and does NOT require disturbance of the earth. Bench rehab's and new concrete collars will be completed on MH's 9855-06 and MH 9855-04 per PCRWRD standard detail 211.
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/18/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 06/18/2024 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 06/18/2024 | TRSP - ROW - Notice of Completion | Passed | ||
| 06/18/2024 | TRSP - ROW - Concrete - Acceptance (Post-Pour) | Passed | ||
| 06/18/2024 | TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) | Passed |