Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Needs Resubmittal
Type:
Right-of-Way (ROW)
Address NEW:
1159 N CRAYCROFT RD
Apply Date:
02/27/2026
Applicant:
Desert Barricade / Eric Horne
Description:
Contractor to perform work within the right-of-way, specifically focusing on the replacement of a water main and its connection to existing infrastructure. This project is anticipated to occur along major roadways and is therefore expected to cause substantial disruptions.

Permit Reviews

Permit Number - TR-ROW-0226-00243
Permit Status: Needs resubmittal
Permit Description: Contractor to perform work within the right-of-way, specifically focusing on the replacement of a water main and its connection to existing infrastructure. This project is anticipated to occur along major roadways and is therefore expected to cause substantial disruptions.
Start Date Submittal Complete Date Status  
06/09/2026 RIGHT-OF-WAY REVIEW REVISION v.1 06/25/2026 REQUIRES RESUBMIT Review Details
03/12/2026 RIGHT-OF-WAY REVIEW v.2 03/19/2026 APPROVED Review Details
02/27/2026 RIGHT-OF-WAY REVIEW v.1 03/12/2026 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-0226-00243
Permit Status: Needs resubmittal
Permit Description: Contractor to perform work within the right-of-way, specifically focusing on the replacement of a water main and its connection to existing infrastructure. This project is anticipated to occur along major roadways and is therefore expected to cause substantial disruptions.
Total Outstanding Activity Conditions - 6
Date Name
03/02/2026 PRE-CON/SIDEWALK
03/02/2026 Traffic Control set-up approved between 7AM - 5PM
03/19/2026 Due to the presence of a bus stop in the area, the contractor is required to contact Joe Garcia, Sun Tran Dispatch, at 520-576-8726 no less than 48 business hours before beginning work to coordinate impacts.
03/19/2026 Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14 Bike Lane Access and Accommodation 1) Posted Speeds 30 Mph or Less – Less than 14 lane - Use of the R4-11 alone is acceptable and preferred over Share The Road sign - 2) Posted Speeds 30 Mph or less – greater than 14 lane - Use of Share The Road sign is preferred 3) Posted Speeds 30 Mph or More – Any Lane Size - Provide a reasonable alternative for cyclists, such as a paved path, space behind barricades, or bike detour. Acceptable to direct cyclists to the sidewalk when properly signed depending on conditions 4) Bike lane to be maintained within Traffic Control closure and Share may Pedestrian detour path with proper R9-6 Sign.
03/19/2026 Traffic control set-up approved between 9AM - 3:30PM
03/19/2026 Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area.

Outstanding Inspections

Permit Status: Needs Resubmittal
Permit Number: TR-ROW-0226-00243
Permite Description: Contractor to perform work within the right-of-way, specifically focusing on the replacement of a water main and its connection to existing infrastructure. This project is anticipated to occur along major roadways and is therefore expected to cause substantial disruptions.
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
07/29/2026 TRSP - ROW - Final N/A Re-inspection required

Completed Inspections

Permit Status: Needs Resubmittal
Permit Number: TR-ROW-0226-00243
Permit Description: Contractor to perform work within the right-of-way, specifically focusing on the replacement of a water main and its connection to existing infrastructure. This project is anticipated to occur along major roadways and is therefore expected to cause substantial disruptions.
Total Completed Inspections - 2
Date Description Inspector Results Comments
03/23/2026 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed I met on site with Edgar Zamora from Innova engineering. We went over the entire pre-reactivity list. Work is beginning immediately and will continue for 3 to 4 Months. Road is not under moratorium and possibly going to be resurfaced under 411.
07/08/2026 TRSP - ROW - Backfill - Placement/Compaction Passed

Documents

File Name Document Type  
COT - TR - ROW PERMIT (SSRS).PDF DOCUMENTS VIEW
DB 72022 - ALL PAGES - WOODLAND AVE SHORT MAIN REPLACEMENT_V2.PDF DOCUMENTS VIEW
DB 72022 - OVERVIEW - WOODLAND AVE SHORT MAIN REPLACMENT_V1.PDF DOCUMENTS VIEW
PJW252-WOODLAND AVE_100 PLANS_01-08-26_FINAL_V1.PDF DOCUMENTS VIEW