Permit: TR-ROW-0226-00243
Permit Details
Status:
Needs Resubmittal
Type:
Right-of-Way (ROW)
Address:
1159 N CRAYCROFT RD
Address NEW:
1159 N CRAYCROFT RD
Apply Date:
02/27/2026
Applicant:
Desert Barricade / Eric Horne
Description:
Contractor to perform work within the right-of-way, specifically focusing on the replacement of a water main and its connection to existing infrastructure. This project is anticipated to occur along major roadways and is therefore expected to cause substantial disruptions.
Permit Reviews
Permit Number - TR-ROW-0226-00243
Permit Status: Needs resubmittal
Permit Description: Contractor to perform work within the right-of-way, specifically focusing on the replacement of a water main and its connection to existing infrastructure. This project is anticipated to occur along major roadways and is therefore expected to cause substantial disruptions.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/09/2026 | RIGHT-OF-WAY REVIEW REVISION v.1 | 06/25/2026 | REQUIRES RESUBMIT |
| 03/12/2026 | RIGHT-OF-WAY REVIEW v.2 | 03/19/2026 | APPROVED |
| 02/27/2026 | RIGHT-OF-WAY REVIEW v.1 | 03/12/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-ROW-0226-00243
Permit Status: Needs resubmittal
Permit Description: Contractor to perform work within the right-of-way, specifically focusing on the replacement of a water main and its connection to existing infrastructure. This project is anticipated to occur along major roadways and is therefore expected to cause substantial disruptions.
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 03/02/2026 | PRE-CON/SIDEWALK |
| 03/02/2026 | Traffic Control set-up approved between 7AM - 5PM |
| 03/19/2026 | Due to the presence of a bus stop in the area, the contractor is required to contact Joe Garcia, Sun Tran Dispatch, at 520-576-8726 no less than 48 business hours before beginning work to coordinate impacts. |
| 03/19/2026 | Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14 Bike Lane Access and Accommodation 1) Posted Speeds 30 Mph or Less – Less than 14 lane - Use of the R4-11 alone is acceptable and preferred over Share The Road sign - 2) Posted Speeds 30 Mph or less – greater than 14 lane - Use of Share The Road sign is preferred 3) Posted Speeds 30 Mph or More – Any Lane Size - Provide a reasonable alternative for cyclists, such as a paved path, space behind barricades, or bike detour. Acceptable to direct cyclists to the sidewalk when properly signed depending on conditions 4) Bike lane to be maintained within Traffic Control closure and Share may Pedestrian detour path with proper R9-6 Sign. |
| 03/19/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 03/19/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
Outstanding Inspections
Permit Status: Needs Resubmittal
Permit Number: TR-ROW-0226-00243
Permite Description: Contractor to perform work within the right-of-way, specifically focusing on the replacement of a water main and its connection to existing infrastructure. This project is anticipated to occur along major roadways and is therefore expected to cause substantial disruptions.
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/29/2026 | TRSP - ROW - Final | N/A | Re-inspection required |
Completed Inspections
Permit Status: Needs Resubmittal
Permit Number: TR-ROW-0226-00243
Permit Description: Contractor to perform work within the right-of-way, specifically focusing on the replacement of a water main and its connection to existing infrastructure. This project is anticipated to occur along major roadways and is therefore expected to cause substantial disruptions.
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/23/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | I met on site with Edgar Zamora from Innova engineering. We went over the entire pre-reactivity list. Work is beginning immediately and will continue for 3 to 4 Months. Road is not under moratorium and possibly going to be resurfaced under 411. | |
| 07/08/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed |