Permit: TR-ROW-0226-00216
Permit Details
Status:
Issued
Type:
Right-of-Way (ROW)
Address:
1150 S PLUMER AV BLDG 1
Address NEW:
1150 S PLUMER AV BLDG 1
Apply Date:
02/22/2026
Applicant:
Description:
The work consists of reconstructing 22nd Street from Kino Parkway to Tucson Boulevard and replacing the existing 4-lane 22nd Street bridge that runs over Barraza-Aviation Parkway and the Union Pacific Railroad (UPRR) with a new 6-lane facility. The facility will consist of two 3-lane bridges with a protected eight-foot multiuse path, one for the eastbound travel direction and one for the westbound travel direction. In addition to the bridge components, improvements shall consist of cast-in-place retaining walls; asphaltic concrete and Portland cement concrete paving, concrete curb/curb and gutter, concrete barrier and sidewalk, paved pathways; a drainage channel, pipe culverts, storm drains, manholes, catch basins and associated inlet and outlet structures; street lighting; landscaping and irrigation; pavement marking and signing; traffic signal improvements at the Tucson Boulevard intersection and Barraza-Aviation Pkwy/Ramp B; sewer modifications; water modifications, and other incidental work.
Permit Reviews
Permit Number - TR-ROW-0226-00216
Permit Status: Issued
Permit Description: The work consists of reconstructing 22nd Street from Kino Parkway to Tucson Boulevard and replacing the existing 4-lane 22nd Street bridge that runs over Barraza-Aviation Parkway and the Union Pacific Railroad (UPRR) with a new 6-lane facility. The facility will consist of two 3-lane bridges with a protected eight-foot multiuse path, one for the eastbound travel direction and one for the westbound travel direction. In addition to the bridge components, improvements shall consist of cast-in-place retaining walls; asphaltic concrete and Portland cement concrete paving, concrete curb/curb and gutter, concrete barrier and sidewalk, paved pathways; a drainage channel, pipe culverts, storm drains, manholes, catch basins and associated inlet and outlet structures; street lighting; landscaping and irrigation; pavement marking and signing; traffic signal improvements at the Tucson Boulevard intersection and Barraza-Aviation Pkwy/Ramp B; sewer modifications; water modifications, and other incidental work.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/23/2026 | RIGHT-OF-WAY REVIEW v.1 | 02/23/2026 | REQUIRES RESUBMIT |
| 02/26/2026 | RIGHT-OF-WAY REVIEW v.3 | 02/26/2026 | APPROVED |
| 02/23/2026 | RIGHT-OF-WAY REVIEW v.2 | 02/26/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-ROW-0226-00216
Permit Status: Issued
Permit Description: The work consists of reconstructing 22nd Street from Kino Parkway to Tucson Boulevard and replacing the existing 4-lane 22nd Street bridge that runs over Barraza-Aviation Parkway and the Union Pacific Railroad (UPRR) with a new 6-lane facility. The facility will consist of two 3-lane bridges with a protected eight-foot multiuse path, one for the eastbound travel direction and one for the westbound travel direction. In addition to the bridge components, improvements shall consist of cast-in-place retaining walls; asphaltic concrete and Portland cement concrete paving, concrete curb/curb and gutter, concrete barrier and sidewalk, paved pathways; a drainage channel, pipe culverts, storm drains, manholes, catch basins and associated inlet and outlet structures; street lighting; landscaping and irrigation; pavement marking and signing; traffic signal improvements at the Tucson Boulevard intersection and Barraza-Aviation Pkwy/Ramp B; sewer modifications; water modifications, and other incidental work.
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 02/26/2026 | The following extended traffic control set-up -times were approved: Full Closure for 957 day 24 hrs day |
| 02/26/2026 | Pre-Activity Meeting w/Inspections Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING |
| 02/26/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 02/26/2026 | Due to the presence of a bus stop in the area, the contractor is required to contact Joe Garcia, Sun Tran Dispatch, at 520-576-8726 no less than 48 business hours before beginning work to coordinate impacts. |