Permit: TR-ROW-0226-00172
Permit Details
Status:
Issued
Type:
Right-of-Way (ROW)
Address:
766 W CALLE DE CASAS LINDAS
Address NEW:
766 W CALLE DE CASAS LINDAS
Apply Date:
02/09/2026
Applicant:
Dustin Huynh
Description:
The scope of work includes furnishing and installing approximately 8000 linear feet of 6-in and 8-in DIP, gate valves, 4 sewer crossings, sidewalk and curb replacement, fire hydrants, concrete-asbestos pipe removal, water meter relocations and service connections. Pavement replacement as indicated on the drawings 06/25/26- TCP was recieved for revision.
Permit Reviews
Permit Number - TR-ROW-0226-00172
Permit Status: Issued
Permit Description: The scope of work includes furnishing and installing approximately 8000 linear feet of 6-in and 8-in DIP, gate valves, 4 sewer crossings, sidewalk and curb replacement, fire hydrants, concrete-asbestos pipe removal, water meter relocations and service connections. Pavement replacement as indicated on the drawings
06/25/26- TCP was recieved for revision.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/04/2026 | RIGHT-OF-WAY REVIEW v.3 | 03/09/2026 | APPROVED |
| 02/10/2026 | RIGHT-OF-WAY REVIEW v.1 | 02/25/2026 | REQUIRES RESUBMIT |
| 06/24/2026 | RIGHT-OF-WAY REVIEW REVISION v.1 | 07/09/2026 | APPROVED |
| 03/02/2026 | RIGHT-OF-WAY REVIEW v.2 | 03/03/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-ROW-0226-00172
Permit Status: Issued
Permit Description: The scope of work includes furnishing and installing approximately 8000 linear feet of 6-in and 8-in DIP, gate valves, 4 sewer crossings, sidewalk and curb replacement, fire hydrants, concrete-asbestos pipe removal, water meter relocations and service connections. Pavement replacement as indicated on the drawings
06/25/26- TCP was recieved for revision.
Total Outstanding Activity Conditions - 8
| Date | Name |
|---|---|
| 02/12/2026 | PRE-CON/SIDEWALK |
| 02/12/2026 | Traffic Control set-up approved between 7AM - 5PM |
| 02/12/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 02/13/2026 | All excavations must be securely plated or backfilled at the end of each workday and during any period when the site is unattended. Plating shall be traffic-rated, flush with the surrounding surface, and properly secured to prevent movement and to maintain public safety |
| 02/13/2026 | Shall coordinate with SANTA CLARA ELEMENTARY SCHOOL well in advance before start of project. Phone: (520) 545-2000 |
| 02/13/2026 | Survey Monument– If survey markers are damaged and/or disturbed during construction, the contractor shall have the marker reset by a registered Land Surveyor. According to state law (ARS 33-103) |
| 02/13/2026 | W Calle Laredo east of 12th ave is subject to a pavement moratorium. A 2-inch mill and overlay, covering one-half the width of the roadway, shall be required. The required pavement restoration treatment shall be confirmed by the ROW Inspector at the preconstruction meeting. |
| 03/03/2026 | Flaggers shall not be placed on or within 200' from Arterial/Collector street |
Outstanding Inspections
Permit Status: Issued
Permit Number: TR-ROW-0226-00172
Permite Description: The scope of work includes furnishing and installing approximately 8000 linear feet of 6-in and 8-in DIP, gate valves, 4 sewer crossings, sidewalk and curb replacement, fire hydrants, concrete-asbestos pipe removal, water meter relocations and service connections. Pavement replacement as indicated on the drawings
06/25/26- TCP was recieved for revision.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/03/2026 | TRSP - ROW - Final | N/A | Re-inspection required | |
| 11/17/2026 | N/A | Re-inspection required |
Completed Inspections
Permit Status: Issued
Permit Number: TR-ROW-0226-00172
Permit Description: The scope of work includes furnishing and installing approximately 8000 linear feet of 6-in and 8-in DIP, gate valves, 4 sewer crossings, sidewalk and curb replacement, fire hydrants, concrete-asbestos pipe removal, water meter relocations and service connections. Pavement replacement as indicated on the drawings
06/25/26- TCP was recieved for revision.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/07/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 07/30/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 07/30/2026 | TRSP - ROW - Bituminous Treatment | Passed | ||
| 07/30/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed |