Permit: TR-ROW-0226-00133
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW)
Address:
983 N VIA ZAHARA DEL SOL
Address NEW:
983 N VIA ZAHARA DEL SOL
Apply Date:
02/02/2026
Applicant:
Uri Daniel Lopez
Description:
Replace three sections of sidewalk, areas are 4'x4'
Permit Reviews
Permit Number - TR-ROW-0226-00133
Permit Status: Complete
Permit Description: Replace three sections of sidewalk, areas are 4'x4'
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/03/2026 | RIGHT-OF-WAY REVIEW v.1 | 02/05/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0226-00133
Permit Status: Complete
Permit Description: Replace three sections of sidewalk, areas are 4'x4'
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 02/05/2026 | Traffic Control set-up approved between 7AM - 5PM |
| 02/05/2026 | PER MUTCD PROPER ADVANCED WARNING SIGNS AHEAD ARE REQUIRED. PEDESTRAIN ACCESS MUST BE PROVIDED AND MAINTAINED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. REPLACE/REPAIR SIDEWALKS PANELS PER PAG STANDARD DETAIL 200/206 |
Outstanding Inspections
Permit Status: Complete
Permit Number: TR-ROW-0226-00133
Permite Description: Replace three sections of sidewalk, areas are 4'x4'
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/17/2026 | TRSP - ROW - Concrete - Acceptance (Post-Pour) | N/A | Deferred |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0226-00133
Permit Description: Replace three sections of sidewalk, areas are 4'x4'
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/11/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 02/13/2026 | TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) | Passed | ||
| 03/06/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 03/06/2026 | TRSP - ROW - Final | Passed |