Permit: TR-ROW-0224-00227
Permit Details
Apply Date:
02/28/2024
Applicant:
BEN LOZANO
Description:
INSTALLATION OF CONDUIT INFRASTRUCTURE TO FACILLITATE INSTALLATION OF FIBER OPTIC CABLING (Permit 2 of 5)
Permit Reviews
Permit Number - TR-ROW-0224-00227
Permit Status: Complete
Permit Description: INSTALLATION OF CONDUIT INFRASTRUCTURE TO FACILLITATE INSTALLATION OF FIBER OPTIC CABLING (Permit 2 of 5)
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/01/2024 | RIGHT-OF-WAY REVIEW v.1 | 03/13/2024 | REQUIRES RESUBMIT |
03/14/2024 | RIGHT-OF-WAY REVIEW v.2 | 03/15/2024 | REQUIRES RESUBMIT |
03/15/2024 | RIGHT-OF-WAY REVIEW v.3 | 03/15/2024 | REQUIRES RESUBMIT |
03/20/2024 | RIGHT-OF-WAY REVIEW v.4 | 03/21/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0224-00227
Permit Status: Complete
Permit Description: INSTALLATION OF CONDUIT INFRASTRUCTURE TO FACILLITATE INSTALLATION OF FIBER OPTIC CABLING (Permit 2 of 5)
Total Outstanding Activity Conditions - 3
Date | Name |
---|---|
03/01/2024 | BUS STOP/ ROUTE |
03/01/2024 | Traffic control set-up approved between 9AM - 3:30PM |
03/21/2024 | Traffic Engineer's comments |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0224-00227
Permit Description: INSTALLATION OF CONDUIT INFRASTRUCTURE TO FACILLITATE INSTALLATION OF FIBER OPTIC CABLING (Permit 2 of 5)
Total Completed Inspections - 7
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/25/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
06/04/2024 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
06/11/2024 | TRSP - ROW - Paving - Subgrade/removal/placement | Passed | ||
06/11/2024 | TRSP - ROW - Barricade Takedown | Passed | ||
06/11/2024 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
06/11/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
06/11/2024 | TRSP - ROW - Bituminous Treatment | Passed |