Permit: TR-ROW-0224-00155
Permit Details
Apply Date:
02/13/2024
Applicant:
Kyle Shepherd
Description:
Repairing Sidewalk Panels and Curbs along south side of Camino Boleadoras From Wilmot road to Kolb Road
Permit Reviews
Permit Number - TR-ROW-0224-00155
Permit Status: Issued
Permit Description: Repairing Sidewalk Panels and Curbs along south side of Camino Boleadoras From Wilmot road to Kolb Road
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/14/2024 | RIGHT-OF-WAY REVIEW v.1 | 02/14/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0224-00155
Permit Status: Issued
Permit Description: Repairing Sidewalk Panels and Curbs along south side of Camino Boleadoras From Wilmot road to Kolb Road
Total Outstanding Activity Conditions - 3
Date | Name |
---|---|
02/14/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
02/14/2024 | Sidewalk installation |
02/14/2024 | Traffic Control set-up approved between 7AM - 5PM |
Outstanding Inspections
Permit Status: Issued
Permit Number: TR-ROW-0224-00155
Permite Description: Repairing Sidewalk Panels and Curbs along south side of Camino Boleadoras From Wilmot road to Kolb Road
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/01/2024 | TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) | N/A | Re-inspection required | site not checked prior to pour |
Completed Inspections
Permit Status: Issued
Permit Number: TR-ROW-0224-00155
Permit Description: Repairing Sidewalk Panels and Curbs along south side of Camino Boleadoras From Wilmot road to Kolb Road
Total Completed Inspections - 5
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/20/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
03/04/2024 | TRSP - ROW - Barricade - Setup/Routine | Passed | inspected by Rick olson | |
05/01/2024 | TRSP - ROW - Barricade Takedown | Passed | ||
05/01/2024 | TRSP - ROW - Final/Close-Out | Passed | work has been completed | |
05/01/2024 | TRSP - ROW - Concrete - Acceptance (Post-Pour) | Passed |