Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Right-of-Way (ROW)
Apply Date:
02/09/2024
Applicant:
Erica Goldston
Description:
The scope of work includes furnishing and installing approximately 900 linear feet of 8-inch DIP and 5,000 linear feet of 6-inch PVC water mains, 170 feet of 6”DIP, gate valves, cut & cap with drain valve assembly, fire hydrants, back flow prevention devices, water meter relocations and service connections. Pavement replacement as indicated on the drawings Updated 5/17/2024 - Traffic Control plan updated to close both Southbound Lanes of Country Club between Flowing Wells and Glenn St. Updated - 5/21/2024 - Request for 60 day Extension as of 5/26/2024 -\ Updated - 10/23/2024 - Request for 30 day Extension as of 10/23/2024

Permit Reviews

Permit Number - TR-ROW-0224-00143
Permit Status: Issued
Permit Description: The scope of work includes furnishing and installing approximately 900 linear feet of 8-inch DIP and 5,000 linear feet of 6-inch PVC water mains, 170 feet of 6”DIP, gate valves, cut & cap with drain valve assembly, fire hydrants, back flow prevention devices, water meter relocations and service connections. Pavement replacement as indicated on the drawings Updated 5/17/2024 - Traffic Control plan updated to close both Southbound Lanes of Country Club between Flowing Wells and Glenn St. Updated - 5/21/2024 - Request for 60 day Extension as of 5/26/2024 -\ Updated - 10/23/2024 - Request for 30 day Extension as of 10/23/2024
Start Date Submittal Complete Date Status  
06/25/2024 RIGHT-OF-WAY REVIEW v.1 06/26/2024 REQUIRES RESUBMIT Review Details
02/16/2024 RIGHT-OF-WAY REVIEW v.3 02/21/2024 APPROVED Review Details
06/28/2024 RIGHT-OF-WAY REVIEW v.2 07/01/2024 REQUIRES RESUBMIT Review Details
07/26/2024 RIGHT-OF-WAY REVIEW REVISION v.2 07/26/2024 REQUIRES RESUBMIT Review Details
07/24/2024 RIGHT-OF-WAY REVIEW REVISION v.1 07/24/2024 REQUIRES RESUBMIT Review Details
07/01/2024 RIGHT-OF-WAY REVIEW v.3 07/08/2024 APPROVED Review Details
07/30/2024 RIGHT-OF-WAY REVIEW REVISION v.3 08/01/2024 APPROVED Review Details
02/12/2024 RIGHT-OF-WAY REVIEW v.2 02/13/2024 REQUIRES RESUBMIT Review Details
05/17/2024 RIGHT-OF-WAY REVIEW v.2 05/21/2024 APPROVED Review Details
02/09/2024 RIGHT-OF-WAY REVIEW v.1 02/09/2024 REQUIRES RESUBMIT Review Details
05/15/2024 RIGHT-OF-WAY REVIEW v.1 05/15/2024 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-0224-00143
Permit Status: Issued
Permit Description: The scope of work includes furnishing and installing approximately 900 linear feet of 8-inch DIP and 5,000 linear feet of 6-inch PVC water mains, 170 feet of 6”DIP, gate valves, cut & cap with drain valve assembly, fire hydrants, back flow prevention devices, water meter relocations and service connections. Pavement replacement as indicated on the drawings Updated 5/17/2024 - Traffic Control plan updated to close both Southbound Lanes of Country Club between Flowing Wells and Glenn St. Updated - 5/21/2024 - Request for 60 day Extension as of 5/26/2024 -\ Updated - 10/23/2024 - Request for 30 day Extension as of 10/23/2024
Total Outstanding Activity Conditions - 6
Date Name
02/09/2024 BUS STOP IN AREA, CONTACT SUN TRAN DISPATCH AT 520-206-8934 AT LEAST 48-BUISNESS HOURS PRIOR TO START OF WORK FOR COORDINATION.
02/09/2024 Traffic Control set-up approved between 7AM - 5PM
02/09/2024 Traffic control set-up approved between 24 Hr
02/09/2024 Pavement Patch type Shall Be in conformance to the current edition of the City of Tucson Public Utility Administrative Manual.
02/09/2024 PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206
02/13/2024 Your project work requires that you contact City of Tucson Environmental Services Department (520-791-3171) at least 24 hours prior to closing any street or alley.

Outstanding Inspections

Permit Status: Issued
Permit Number: TR-ROW-0224-00143
Permite Description: The scope of work includes furnishing and installing approximately 900 linear feet of 8-inch DIP and 5,000 linear feet of 6-inch PVC water mains, 170 feet of 6”DIP, gate valves, cut & cap with drain valve assembly, fire hydrants, back flow prevention devices, water meter relocations and service connections. Pavement replacement as indicated on the drawings Updated 5/17/2024 - Traffic Control plan updated to close both Southbound Lanes of Country Club between Flowing Wells and Glenn St. Updated - 5/21/2024 - Request for 60 day Extension as of 5/26/2024 -\ Updated - 10/23/2024 - Request for 30 day Extension as of 10/23/2024
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
TRSP - ROW - Paving - Subgrade/removal/placement N/A Requested
TRSP - ROW - Barricade Takedown N/A Scheduled
10/21/2024 TRSP - ROW - Final/Close-Out N/A Re-inspection required
10/21/2024 TRSP - ROW - Concrete - Acceptance (Post-Pour) N/A Re-inspection required
10/21/2024 TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) N/A Re-inspection required

Completed Inspections

Permit Status: Issued
Permit Number: TR-ROW-0224-00143
Permit Description: The scope of work includes furnishing and installing approximately 900 linear feet of 8-inch DIP and 5,000 linear feet of 6-inch PVC water mains, 170 feet of 6”DIP, gate valves, cut & cap with drain valve assembly, fire hydrants, back flow prevention devices, water meter relocations and service connections. Pavement replacement as indicated on the drawings Updated 5/17/2024 - Traffic Control plan updated to close both Southbound Lanes of Country Club between Flowing Wells and Glenn St. Updated - 5/21/2024 - Request for 60 day Extension as of 5/26/2024 -\ Updated - 10/23/2024 - Request for 30 day Extension as of 10/23/2024
Total Completed Inspections - 4
Date Description Inspector Results Comments
02/29/2024 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
05/31/2024 TRSP - ROW - Barricade - Setup/Routine Passed
06/26/2024 TRSP - ROW - SWBMP Passed
07/29/2024 TRSP - ROW - Backfill - Placement/Compaction Passed

Scheduled Inspections

Scheduled Inspections - TR-ROW-0224-00143
Status: Issued
Description: The scope of work includes furnishing and installing approximately 900 linear feet of 8-inch DIP and 5,000 linear feet of 6-inch PVC water mains, 170 feet of 6”DIP, gate valves, cut & cap with drain valve assembly, fire hydrants, back flow prevention devices, water meter relocations and service connections. Pavement replacement as indicated on the drawings Updated 5/17/2024 - Traffic Control plan updated to close both Southbound Lanes of Country Club between Flowing Wells and Glenn St. Updated - 5/21/2024 - Request for 60 day Extension as of 5/26/2024 -\ Updated - 10/23/2024 - Request for 30 day Extension as of 10/23/2024
Scheduled Date Description Entered By Entered Date
11/29/2024 TRSP - ROW - Barricade Takedown Scheduled
For information about today’s scheduled inspections please refer to the PDSD Daily Inspections Dashboards (Desktop) PDSD Daily Inspections Dashboards (Mobile) .

Documents

File Name Document Type  
ADDITIONAL TRAFFIC CONTROL-REVISED 7.29.24_V3.PDF DOCUMENTS VIEW
COT - TR - ROW PERMIT.PDF DOCUMENTS VIEW
ADD' TRAFFIC CONTROL_V1.PDF DOCUMENTS VIEW
COT - TR - ROW PERMIT.PDF DOCUMENTS VIEW
HUNTER REVISION NARRATIVE_V2.PDF DOCUMENTS VIEW
HUNTER - LA MADERA PH3 WORK AREA REVISION NARRATIVE_V1.PDF DOCUMENTS VIEW
HUNTER REVISED TCP'S COUNTRY CLUB RD_V1.PDF DOCUMENTS VIEW
COT - TR - ROW PERMIT.PDF DOCUMENTS VIEW
LA MADERA PHASE III _CONSTRUCTION DRAWING REV 1_V1.PDF DOCUMENTS VIEW
LA MADERA PH3 - TCP_V2.PDF DOCUMENTS VIEW
LA MADERA PH3 ROW MAP_V1.PDF DOCUMENTS VIEW