Permit: TR-ROW-0224-00126
Permit Details
Apply Date:
02/05/2024
Applicant:
Description:
Contractor excavating for Electric/Gas/Cable joint utility trench on E Wingate Blvd in the ROW for new subdivision Bella Tierra Phase 3.
Permit Reviews
Permit Number - TR-ROW-0224-00126
Permit Status: Issued
Permit Description: Contractor excavating for Electric/Gas/Cable joint utility trench on E Wingate Blvd in the ROW for new subdivision Bella Tierra Phase 3.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/06/2024 | RIGHT-OF-WAY REVIEW v.1 | 02/07/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0224-00126
Permit Status: Issued
Permit Description: Contractor excavating for Electric/Gas/Cable joint utility trench on E Wingate Blvd in the ROW for new subdivision Bella Tierra Phase 3.
Total Outstanding Activity Conditions - 4
Date | Name |
---|---|
02/06/2024 | The following extended traffic control set-up times were approved: 24 Hr |
02/06/2024 | Traffic Control set-up approved between 7AM - 5PM |
11/22/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
11/22/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TR-ROW-0224-00126
Permite Description: Contractor excavating for Electric/Gas/Cable joint utility trench on E Wingate Blvd in the ROW for new subdivision Bella Tierra Phase 3.
Total Outstanding Inspections - 5
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/17/2024 | TRSP - ROW - Barricade - Setup/Routine | N/A | Complete (Recurring) | work in progress |
05/17/2024 | TRSP - ROW - Paving - Subgrade/removal/placement | N/A | Complete (Recurring) | work in progress with pia will reach out to Brian to renew permit |
05/17/2024 | TRSP - ROW - Barricade Takedown | N/A | Complete (Recurring) | work in progress |
05/17/2024 | TRSP - ROW - Backfill - Placement/Compaction | N/A | Complete (Recurring) | work in orogress |
05/17/2024 | TRSP - ROW - Final/Close-Out | N/A | Complete (Recurring) | work in origress |
Completed Inspections
Permit Status: Issued
Permit Number: TR-ROW-0224-00126
Permit Description: Contractor excavating for Electric/Gas/Cable joint utility trench on E Wingate Blvd in the ROW for new subdivision Bella Tierra Phase 3.
Total Completed Inspections - 1
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/17/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed |