Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Right-of-Way (ROW)
Address NEW:
1302 S AVENIDA VEGA
Apply Date:
02/16/2023
Applicant:
Cameron Bonner
Description:
Site 1 - This location is located on 22nd St. in front of Palo Verde HS. Ellison-Mills construction is coordinating the work with Palo Verde HS to take place during the spring break during the week of 3/20 to 3/24/2023. Install Approximately 315 LF of 8" Cured in Place Pipe. The Cured in Place Pipe is a trench-less technology for sewer rehabilitation and does NOT require disturbance of the earth. New concrete collars will be completed on MH's 5486-04 and MH 5486-05 per PCRWRD standard detail 211/212.

Permit Reviews

Permit Number - TR-ROW-0223-00393
Permit Status: Complete
Permit Description: Site 1 - This location is located on 22nd St. in front of Palo Verde HS. Ellison-Mills construction is coordinating the work with Palo Verde HS to take place during the spring break during the week of 3/20 to 3/24/2023. Install Approximately 315 LF of 8" Cured in Place Pipe. The Cured in Place Pipe is a trench-less technology for sewer rehabilitation and does NOT require disturbance of the earth. New concrete collars will be completed on MH's 5486-04 and MH 5486-05 per PCRWRD standard detail 211/212.
Start Date Submittal Complete Date Status  
03/05/2023 RIGHT-OF-WAY REVIEW v.1 03/09/2023 APPROVED Review Details

Conditions

Permit Number - TR-ROW-0223-00393
Permit Status: Complete
Permit Description: Site 1 - This location is located on 22nd St. in front of Palo Verde HS. Ellison-Mills construction is coordinating the work with Palo Verde HS to take place during the spring break during the week of 3/20 to 3/24/2023. Install Approximately 315 LF of 8" Cured in Place Pipe. The Cured in Place Pipe is a trench-less technology for sewer rehabilitation and does NOT require disturbance of the earth. New concrete collars will be completed on MH's 5486-04 and MH 5486-05 per PCRWRD standard detail 211/212.
Date Description Comments
03/08/2023 BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AND/OR BEA PAULUS AT 520-206-8826 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION. ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRATIVE MANUAL. SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D.
03/08/2023 Traffic control set-up approved between 9AM - 3:30PM

Completed Inspections

Permit Status: Complete
Permit Number: TR-ROW-0223-00393
Permit Description: Site 1 - This location is located on 22nd St. in front of Palo Verde HS. Ellison-Mills construction is coordinating the work with Palo Verde HS to take place during the spring break during the week of 3/20 to 3/24/2023. Install Approximately 315 LF of 8" Cured in Place Pipe. The Cured in Place Pipe is a trench-less technology for sewer rehabilitation and does NOT require disturbance of the earth. New concrete collars will be completed on MH's 5486-04 and MH 5486-05 per PCRWRD standard detail 211/212.
Total Completed Inspections - 3
Date Description Inspector Results Comments
07/25/2023 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
07/25/2023 TRSP - ROW - Recurring Passed
07/25/2023 TRSP - ROW - Final/Close-Out Passed

Documents

File Name Document Type  
COT - TR - ROW PERMIT.PDF DOCUMENTS VIEW
322033 - SITE 1 FMP MAP (6782 E 22ND ST)_V1.PDF DOCUMENTS VIEW
DB 67416 - PAGE 1 - 6782 E 22ND ST - SHOULDERS - 322033_V1.PDF DOCUMENTS VIEW