Permit Details

Status:
Complete
Type:
Right-of-Way (ROW)
Address:
3434 E 22ND ST
Address NEW:
3434 E 22ND ST
Apply Date:
01/29/2026
Applicant:
Caitlin Ripley - Southwest Barricades
Description:
Valve Adjustments, Survey Monument

Permit Reviews

Permit Number - TR-ROW-0126-00119
Permit Status: Complete
Permit Description: Valve Adjustments, Survey Monument
Start Date Submittal Complete Date Status  
02/05/2026 RIGHT-OF-WAY REVIEW v.2 02/06/2026 APPROVED Review Details
01/29/2026 RIGHT-OF-WAY REVIEW v.1 02/04/2026 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-0126-00119
Permit Status: Complete
Permit Description: Valve Adjustments, Survey Monument
Total Outstanding Activity Conditions - 6
Date Name
02/03/2026 Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area.
02/06/2026 All excavations must be securely plated or backfilled at the end of each workday and during any period when the site is unattended. Plating shall be traffic-rated, flush with the surrounding surface, and properly secured to prevent movement and to maintain public safety
02/06/2026 Approved Temporary Noise Exemption required prior to Night work being performed within the City of Tucson Right of Way
02/06/2026 Due to the presence of a bus stop in the area, the contractor is required to contact Joe Garcia, Sun Tran Dispatch, at 520-576-8726 no less than 48 business hours before beginning work to coordinate impacts
02/06/2026 Pedestrian Detour: Any temporary pedestrian detour shall be ADA compliant at all times and provide a continuous, accessible route and maintained in a safe and accessible condition for the duration of construction.
02/06/2026 S Palo Verde is subject to a pavement moratorium. A 2-inch mill and overlay, covering one-half the width of the roadway, shall be required. The required pavement restoration treatment shall be confirmed by the ROW Inspector at the preconstruction meeting

Completed Inspections

Permit Status: Complete
Permit Number: TR-ROW-0126-00119
Permit Description: Valve Adjustments, Survey Monument
Total Completed Inspections - 4
Date Description Inspector Results Comments
03/17/2026 TRSP - ROW - Barricade - Setup/Routine Passed Signs and message boards per TCP
03/17/2026 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed Area to original or better.
03/17/2026 TRSP - ROW - Backfill - Placement/Compaction Passed Backfill per utility requirements
03/17/2026 TRSP - ROW - Final Passed Area is to original or better.