Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Right-of-Way (ROW)
Address:
3434 E 22ND ST
Address NEW:
3434 E 22ND ST
Apply Date:
01/29/2026
Applicant:
Caitlin Ripley - Southwest Barricades
Description:
Valve Adjustments, Survey Monument

Permit Reviews

Permit Number - TR-ROW-0126-00119
Permit Status: Issued
Permit Description: Valve Adjustments, Survey Monument
Start Date Submittal Complete Date Status  
02/05/2026 RIGHT-OF-WAY REVIEW v.2 02/06/2026 APPROVED Review Details
01/29/2026 RIGHT-OF-WAY REVIEW v.1 02/04/2026 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-0126-00119
Permit Status: Issued
Permit Description: Valve Adjustments, Survey Monument
Total Outstanding Activity Conditions - 6
Date Name
02/03/2026 Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area.
02/06/2026 All excavations must be securely plated or backfilled at the end of each workday and during any period when the site is unattended. Plating shall be traffic-rated, flush with the surrounding surface, and properly secured to prevent movement and to maintain public safety
02/06/2026 Approved Temporary Noise Exemption required prior to Night work being performed within the City of Tucson Right of Way
02/06/2026 Due to the presence of a bus stop in the area, the contractor is required to contact Joe Garcia, Sun Tran Dispatch, at 520-576-8726 no less than 48 business hours before beginning work to coordinate impacts
02/06/2026 Pedestrian Detour: Any temporary pedestrian detour shall be ADA compliant at all times and provide a continuous, accessible route and maintained in a safe and accessible condition for the duration of construction.
02/06/2026 S Palo Verde is subject to a pavement moratorium. A 2-inch mill and overlay, covering one-half the width of the roadway, shall be required. The required pavement restoration treatment shall be confirmed by the ROW Inspector at the preconstruction meeting

Documents

File Name Document Type  
COT - TR - ROW PERMIT (SSRS).PDF DOCUMENTS VIEW
1 OF 7_ SHEET 1 WATER PLAN REV.1 (003)_V1.PDF DOCUMENTS VIEW
25-0104B_V2.PDF DOCUMENTS VIEW
25-0104C_V2.PDF DOCUMENTS VIEW
25-0104_V2.PDF DOCUMENTS VIEW