Permit: TR-ROW-0126-00059
Permit Details
Apply Date:
01/20/2026
Applicant:
Description:
New water lines will be installed into the property.
Permit Reviews
Permit Number - TR-ROW-0126-00059
Permit Status: Complete
Permit Description: New water lines will be installed into the property.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/20/2026 | RIGHT-OF-WAY REVIEW v.1 | 01/21/2026 | REQUIRES RESUBMIT |
| 01/21/2026 | RIGHT-OF-WAY REVIEW v.2 | 01/22/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0126-00059
Permit Status: Complete
Permit Description: New water lines will be installed into the property.
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 01/21/2026 | ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14 |
| 01/21/2026 | PAVEMENT MORATORIUM: ANY NEW ASPHALT THAT IS DISTURBED WILL REQUIRE A 2” MILL AND OVERLAY FOR 25’ IN EACH DIRECTION FROM THE OUTSIDE OF THE CUT FOR ALL EFFECTED TRAVEL LANES. |
| 01/21/2026 | Traffic Control set-up approved between 7AM - 5PM |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0126-00059
Permit Description: New water lines will be installed into the property.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/04/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | Inspection not needed worked under an emergency and all work was completed, and then the F11 came through and covered up evidence | |
| 03/04/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | Inspection not needed worked under an emergency and all work was completed, and then the 411 came through and covered up evidence all looks to be correct preactivity was held under previous permit | |
| 03/04/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed | Inspection not needed worked under an emergency and all work was completed, and then the 411 came through and covered up evidence all looks to be correct | |
| 03/04/2026 | TRSP - ROW - Final | Passed |