Permit Details

Status:
Complete
Type:
Right-of-Way (ROW)
Address:
1100 W GLENN ST
Address NEW:
1100 W GLENN ST
Apply Date:
01/07/2025
Applicant:
James Degrood
Description:
Roadway material sampling for PROP 411 project

Permit Reviews

Permit Number - TR-ROW-0125-00028
Permit Status: Complete
Permit Description: Roadway material sampling for PROP 411 project
Start Date Submittal Complete Date Status  
01/07/2025 RIGHT-OF-WAY REVIEW v.1 01/10/2025 REQUIRES RESUBMIT Review Details
01/29/2025 RIGHT-OF-WAY REVIEW v.2 01/30/2025 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-0125-00028
Permit Status: Complete
Permit Description: Roadway material sampling for PROP 411 project
Total Outstanding Activity Conditions - 2
Date Name
01/10/2025 PRE-CON/PAVEMENT/SIDEWALK
01/10/2025 Traffic control set-up approved between 9AM - 3:30PM

Conditions

Permit Number - TR-ROW-0125-00028
Permit Status: Complete
Permit Description: Roadway material sampling for PROP 411 project
Date Description Comments
01/10/2025 This project is located in an Archaeological Sensitivity Zone. An Archaeological Monitor hired by the permit applicant is required to be on-site during any digging, unless a waiver is issued. Monitoring reports are to be submitted to Historic Preservation Office, City of Tucson, P.O. Box 27210, Tucson, AZ 85726.** Please contact Jodie Brown at Jodie.Brown@tucsonaz.gov with any questions.

Completed Inspections

Permit Status: Complete
Permit Number: TR-ROW-0125-00028
Permit Description: Roadway material sampling for PROP 411 project
Total Completed Inspections - 3
Date Description Inspector Results Comments
02/26/2025 TRSP - ROW - Barricade - Setup/Routine Passed
02/26/2025 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
02/26/2025 TRSP - ROW - Final Passed