Permit: TR-ROW-0124-00062
Permit Details
Apply Date:
01/11/2024
Applicant:
Brandy Burke
Description:
This work is to replace the sidewalk that was removed in order to install utilities underground which was permitted by TEP, Cox, & Lumen. Contractor anticipates the sidewalk work being complete by 01/31/2024.
Permit Reviews
Permit Number - TR-ROW-0124-00062
Permit Status: Complete
Permit Description: This work is to replace the sidewalk that was removed in order to install utilities underground which was permitted by TEP, Cox, & Lumen. Contractor anticipates the sidewalk work being complete by 01/31/2024.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/12/2024 | RIGHT-OF-WAY REVIEW v.1 | 01/17/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0124-00062
Permit Status: Complete
Permit Description: This work is to replace the sidewalk that was removed in order to install utilities underground which was permitted by TEP, Cox, & Lumen. Contractor anticipates the sidewalk work being complete by 01/31/2024.
Total Outstanding Activity Conditions - 3
Date | Name |
---|---|
01/16/2024 | This project is located in an Archaeological Sensitivity Zone. An Archaeological Monitor hired by the permit applicant is required to be on-site during any digging, unless a waiver is issued. Monitoring reports are to be submitted to Historic Preservation Office, City of Tucson, P.O. Box 27210, Tucson, AZ 85726.** Please contact Jodie Brown at Jodie.Brown@tucsonaz.gov with any questions. |
01/16/2024 | Sidewalk replacement |
01/16/2024 | Traffic Control set-up approved between 7AM - 5PM |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0124-00062
Permit Description: This work is to replace the sidewalk that was removed in order to install utilities underground which was permitted by TEP, Cox, & Lumen. Contractor anticipates the sidewalk work being complete by 01/31/2024.
Total Completed Inspections - 4
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/24/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
02/16/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
02/06/2024 | TRSP - ROW - Concrete - Acceptance (Post-Pour) | Passed | ||
02/06/2024 | TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) | Passed |