Permit: TR-FBR-1126-00031
Permit Details
Status:
Inspections
Type:
Fiber Permit
Address:
6700 E NICARAGUA DR
Address NEW:
6700 E NICARAGUA DR
Apply Date:
11/03/2026
Applicant:
Andrew Thome-Hernandez
Description:
IDK #26 - 0591 - Tucson - Zone 204.1 Permit SOW: Scope of Work falls between E Nicaragua Dr to E Victoria St and between S Calle Polar and S Austin PL. Ideatek is Expanding Fiber Optic Cable Network in Tucson. This fiber be placed in Tucson Road Right of Way. Fiber will be buried min 36" deep in ROW. Work will be done with Directional Bore Machines by placing 1.25"-2" Sch 40 Orange Duct. Backbone fiber Count ranges from 48ct up 96ct and pulled through duct. Vault and service pedestals to be placed along route to serve as splicing points. PLEASE SEE ATTACHED APPROVED SITE PLANS AND TCP FOR BETTER DETAILS. Ideatek Project Manager Contact: Ron Willey 816-661-7440 rwilley@ideatek.com
Permit Reviews
Permit Number - TR-FBR-1126-00031
Permit Status: Inspections
Permit Description: IDK #26 - 0591 - Tucson - Zone 204.1
Permit SOW: Scope of Work falls between E Nicaragua Dr to E Victoria St and between S Calle Polar and S Austin PL.
Ideatek is Expanding Fiber Optic Cable Network in Tucson. This fiber be placed in Tucson Road Right of Way. Fiber will be buried min 36" deep in ROW. Work will be done with Directional Bore Machines by placing 1.25"-2" Sch 40 Orange Duct. Backbone fiber Count ranges from 48ct up 96ct and pulled through duct. Vault and service pedestals to be placed along route to serve as splicing points.
PLEASE SEE ATTACHED APPROVED SITE PLANS AND TCP FOR BETTER DETAILS.
Ideatek Project Manager Contact:
Ron Willey
816-661-7440
rwilley@ideatek.com
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/04/2026 | RIGHT-OF-WAY SIMPLE REVIEW v.2 | 11/05/2026 | APPROVED |
| 11/03/2026 | RIGHT-OF-WAY SIMPLE REVIEW v.1 | 11/03/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-FBR-1126-00031
Permit Status: Inspections
Permit Description: IDK #26 - 0591 - Tucson - Zone 204.1
Permit SOW: Scope of Work falls between E Nicaragua Dr to E Victoria St and between S Calle Polar and S Austin PL.
Ideatek is Expanding Fiber Optic Cable Network in Tucson. This fiber be placed in Tucson Road Right of Way. Fiber will be buried min 36" deep in ROW. Work will be done with Directional Bore Machines by placing 1.25"-2" Sch 40 Orange Duct. Backbone fiber Count ranges from 48ct up 96ct and pulled through duct. Vault and service pedestals to be placed along route to serve as splicing points.
PLEASE SEE ATTACHED APPROVED SITE PLANS AND TCP FOR BETTER DETAILS.
Ideatek Project Manager Contact:
Ron Willey
816-661-7440
rwilley@ideatek.com
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 11/05/2026 | Your project work requires that you contact City of Tucson Environmental Services Department (520-791-3171) at least 24 hours prior to closing any street or alley. |
| 11/05/2026 | LANDSCAPE |
| 11/05/2026 | Pavement moratorium |
| 11/05/2026 | Pre- activity/construction meeting |
Completed Inspections
Permit Status: Inspections
Permit Number: TR-FBR-1126-00031
Permit Description: IDK #26 - 0591 - Tucson - Zone 204.1
Permit SOW: Scope of Work falls between E Nicaragua Dr to E Victoria St and between S Calle Polar and S Austin PL.
Ideatek is Expanding Fiber Optic Cable Network in Tucson. This fiber be placed in Tucson Road Right of Way. Fiber will be buried min 36" deep in ROW. Work will be done with Directional Bore Machines by placing 1.25"-2" Sch 40 Orange Duct. Backbone fiber Count ranges from 48ct up 96ct and pulled through duct. Vault and service pedestals to be placed along route to serve as splicing points.
PLEASE SEE ATTACHED APPROVED SITE PLANS AND TCP FOR BETTER DETAILS.
Ideatek Project Manager Contact:
Ron Willey
816-661-7440
rwilley@ideatek.com
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/13/2026 | Pre-Activity Field Meeting | Passed | Met with Erick from E&E on-site. advised of ROW requirements. Advised of compaction requirements for work area in dirt alleys and moratorium restoration if required. Advised if extended hour of work were needed or if closures of alleys was required to submit requests prior to activity. Advised to make notifications regarding trash pick up. |