Permit: TD-DEV-1022-00001
Permit Details
Apply Date:
10/28/2022
Applicant:
Lexy Wellott
Description:
Restricted Records/ Install new playground and dog park fence/equipment
Permit Reviews
Permit Number - TD-DEV-1022-00001
Permit Status: Complete
Permit Description: Restricted Records/ Install new playground and dog park fence/equipment
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/28/2024 | DEVELOPMENT PACKAGE REVIEW v.3 | 03/28/2024 | APPROVED |
01/03/2024 | DEVELOPMENT PACKAGE REVIEW v.1 | 01/10/2024 | REQUIRES RESUBMIT |
04/24/2023 | DEVELOPMENT PACKAGE REVIEW v.3 | 07/06/2023 | APPROVED |
01/16/2024 | DEVELOPMENT PACKAGE REVIEW v.2 | 01/31/2024 | REQUIRES RESUBMIT |
10/28/2022 | DEVELOPMENT PACKAGE REVIEW v.1 | 01/31/2023 | REQUIRES RESUBMIT |
03/28/2023 | DEVELOPMENT PACKAGE REVIEW v.2 | 04/12/2023 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Complete
Permit Number: TD-DEV-1022-00001
Permite Description: Restricted Records/ Install new playground and dog park fence/equipment
Total Outstanding Inspections - 10
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/02/2023 | PDSD Site/Engineering Division - NPPO | N/A | Partial Pass | Contractor set up the nursery on the other side of Lincoln Park. Everything looks good there. |
11/16/2023 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | |
11/13/2023 | ENGR - Drainage Structures | N/A | Not Ready | No rebar to inspect it at this time |
11/16/2023 | Final inspection to ensure all landscape and water harvesting SITE | N/A | Not Ready | |
11/13/2023 | SITE - SWPPP Correction Notice | N/A | Complete (Recurring) | No concerns at this time. I drove around both parts of the park and everything looks good contractors not on site. |
11/16/2023 | SITE | N/A | Not Ready | |
11/13/2023 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | |
11/13/2023 | SITE - Stormwater Setup and Controls | N/A | Complete (Recurring) | No concerns at this time. I drove around both parts of the park and everything looks good contractors not on site. |
05/17/2024 | COT - FCON - Fire - Final | N/A | Not Applicable | |
11/13/2023 | COT - ENGR - Stormwater | N/A | Complete (Recurring) | No concerns at this time. I drove around both parts of the park and everything looks good contractors not on site. |
Completed Inspections
Permit Status: Complete
Permit Number: TD-DEV-1022-00001
Permit Description: Restricted Records/ Install new playground and dog park fence/equipment
Total Completed Inspections - 14
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/16/2023 | ENGR - Drainage Structures | Passed | ||
11/16/2023 | SITE - SWPPP Correction Notice | Passed | ||
11/16/2023 | City of Tucson (COT) Planning and Development Services Engineering (ENGR) Zoning Compliance Inspection | Passed | ||
11/16/2023 | COT - ENGR - Signage Final | Passed | ||
05/17/2024 | PDSD Engineering Division Pre-Construction SITE | Passed | ||
05/21/2024 | LAND Landscape Appearance & Function Final | Passed | in the sidewalk in the island area from the west parking lot going towards the dog park needs railing exceeds the 5% running slope. The walkway from the parking lot towards the dog park area NONCOMPLIANT exceeds 5% running slope in the handicap ramp for this north by the tree is noncompliant. The playground area east of the shade area needs a railing and the sidewalk east of the shade area needs railing. OK for level four. | |
05/21/2024 | ENGR Grading Final | Passed | ||
06/04/2024 | SITE - Zoning Final | Passed | ||
06/04/2024 | SITE - Stormwater Final Inspection | Passed | ||
06/04/2024 | COT - ENGR - Stormwater | Passed | ||
06/04/2024 | Passed | |||
06/04/2024 | Passed | |||
06/06/2024 | ENGR Engineering Final | Passed | The cross slopes have been repaired in pedestrian access lane meets the required 5% or less cross slope for ADA access. | |
06/06/2024 | ENGR Paving | Passed |