Permit: TD-DEV-0923-00403
Permit Details
Apply Date:
09/22/2023
Applicant:
Amy Peron
Description:
Restricted Access - *Revision # 2 started 4/1/24 (landscaping)* Replacement of the existing tennis courts and basketball court with (2) new covered basketball courts and (6) new pickleball courts.
Permit Reviews
Permit Number - TD-DEV-0923-00403
Permit Status: Issued
Permit Description: Restricted Access - *Revision # 2 started 4/1/24 (landscaping)* Replacement of the existing tennis courts and basketball court with (2) new covered basketball courts and (6) new pickleball courts.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/29/2025 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 10/06/2025 | APPROVED |
| 09/25/2023 | DEVELOPMENT PACKAGE NEW v.1 | 09/28/2023 | REQUIRES RESUBMIT |
| 10/25/2023 | DEVELOPMENT PACKAGE NEW v.2 | 11/17/2023 | REQUIRES RESUBMIT |
| 04/01/2024 | DEVELOPMENT PACKAGE NEW v.1 | 04/25/2024 | APPROVED |
| 11/28/2023 | DEVELOPMENT PACKAGE NEW v.3 | 12/11/2023 | APPROVED |
Outstanding Inspections
Permit Status: Issued
Permit Number: TD-DEV-0923-00403
Permite Description: Restricted Access - *Revision # 2 started 4/1/24 (landscaping)* Replacement of the existing tennis courts and basketball court with (2) new covered basketball courts and (6) new pickleball courts.
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/31/2024 | COT - ENGR - Stormwater | N/A | Complete (Recurring) | All items have been corrected that were listed, these areas need to be maintained as the project moves forward. |
| 04/25/2025 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | Swppp is good, ok to schedule at 4 weeks until we see a rain event. |
| 04/28/2025 | SITE - Stormwater Final Inspection | N/A | Partial Pass | contractor needs complete the project before I finalize the stormwater |
| 11/05/2025 | ENGR Engineering Final | N/A | Partial Pass | Revision required to reflect as-built status. |
Completed Inspections
Permit Status: Issued
Permit Number: TD-DEV-0923-00403
Permit Description: Restricted Access - *Revision # 2 started 4/1/24 (landscaping)* Replacement of the existing tennis courts and basketball court with (2) new covered basketball courts and (6) new pickleball courts.
Total Completed Inspections - 7
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/31/2024 | NPPO Pre-Construction | Passed | I had a conversation with the contractor about moving the entrance gate that’s across the street from the school. Informed him he needed to move it to the east side of the park so there’s no hazard to the children walking into the school area. | |
| 11/07/2024 | PDSD Engineering Division Pre-Construction SITE | Passed | Joe Barr is the city PM on this job and should had scheduled the pre-con before this job started. | |
| 11/07/2024 | SITE - Stormwater Setup and Controls | Passed | ||
| 04/24/2025 | COT - SITE - Zoning Intermediate | Passed | inform the contractor needed to clean out all the trenches before backfilling and before put it in the top layer, bedding sand | |
| 04/24/2025 | SITE - Zoning Compliance | Passed | inform the contractor needed to clean out all the trenches before backfilling and before put it in the top layer, bedding sand | |
| 04/28/2025 | Passed | |||
| 04/28/2025 | ENGR - Drainage Structures | Passed |