Permit: TD-DEV-0725-00198
Permit Details
Status:
Complete
Type:
Development Package
Address:
10 N CONGRESS TE UNIT 2
Address NEW:
10 N CONGRESS TE UNIT 2
Apply Date:
07/29/2025
Applicant:
alex enoch
Description:
new detached adu
Permit Reviews
Permit Number - TD-DEV-0725-00198
Permit Status: Complete
Permit Description: new detached adu
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/07/2025 | DEVELOPMENT PACKAGE NEW v.2 | 08/08/2025 | REQUIRES RESUBMIT |
| 07/30/2025 | DEVELOPMENT PACKAGE NEW v.1 | 08/01/2025 | REQUIRES RESUBMIT |
| 08/12/2025 | DEVELOPMENT PACKAGE NEW v.3 | 09/08/2025 | REQUIRES RESUBMIT |
| 09/22/2025 | DEVELOPMENT PACKAGE NEW v.4 | 09/24/2025 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TD-DEV-0725-00198
Permite Description: new detached adu
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/24/2026 | ENGR Engineering Final | N/A | Partial Pass | contractor needs to address the riprap area in the back of the house and in front of the house at the front door |
Completed Inspections
Permit Status: Complete
Permit Number: TD-DEV-0725-00198
Permit Description: new detached adu
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/13/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | I informed the contractor he can proceed with construction. Also informed him we needed all the test, compact, asphalt, concrete, etc. must be on site at all times and have a hard copy of all the test. | |
| 04/14/2026 | SITE - Zoning Final | Passed | ||
| 02/26/2026 | Passed | |||
| 02/26/2026 | ENGR Engineering Final | Passed |