Permit Details

Status:
Inspections
Type:
Development Package
Address:
130 S SCOTT AV
Address NEW:
130 S SCOTT AV
Apply Date:
03/05/2026
Applicant:
Joe Alitiem
Description:
Install a parking structure solar array. SCOPE OF WORK SYSTEM SIZE : STC : 84 X 545W= 45.78 KW DC PTC : 84 X 502.2W = 42.18 KW DC AC SIZE: 60.0 KW AC 84) LONGI SOLAR LR5-72HBD-545M (545W) MODULES (01) SOLIS S5-GC60K-LV-US (208V) INVERTER. Install a new 75KVA TRANSFORMER PRIMARY-240V DELTA SECONDARY-120/208V WYE

Permit Reviews

Permit Number - TD-DEV-0326-00054
Permit Status: Inspections
Permit Description: Install a parking structure solar array. SCOPE OF WORK SYSTEM SIZE : STC : 84 X 545W= 45.78 KW DC PTC : 84 X 502.2W = 42.18 KW DC AC SIZE: 60.0 KW AC 84) LONGI SOLAR LR5-72HBD-545M (545W) MODULES (01) SOLIS S5-GC60K-LV-US (208V) INVERTER. Install a new 75KVA TRANSFORMER PRIMARY-240V DELTA SECONDARY-120/208V WYE
Start Date Submittal Complete Date Status  
04/06/2026 DEVELOPMENT PACKAGE NEW v.3 04/28/2026 REQUIRES RESUBMIT Review Details
03/06/2026 DEVELOPMENT PACKAGE NEW v.1 03/10/2026 REQUIRES RESUBMIT Review Details
05/06/2026 DEVELOPMENT PACKAGE NEW v.4 05/06/2026 APPROVED Review Details
03/12/2026 DEVELOPMENT PACKAGE NEW v.2 03/27/2026 REQUIRES RESUBMIT Review Details

Completed Inspections

Permit Status: Inspections
Permit Number: TD-DEV-0326-00054
Permit Description: Install a parking structure solar array. SCOPE OF WORK SYSTEM SIZE : STC : 84 X 545W= 45.78 KW DC PTC : 84 X 502.2W = 42.18 KW DC AC SIZE: 60.0 KW AC 84) LONGI SOLAR LR5-72HBD-545M (545W) MODULES (01) SOLIS S5-GC60K-LV-US (208V) INVERTER. Install a new 75KVA TRANSFORMER PRIMARY-240V DELTA SECONDARY-120/208V WYE
Total Completed Inspections - 1
Date Description Inspector Results Comments
05/11/2026 PDSD Engineering Division Pre-Construction SITE Passed