Permit: TD-DEV-0123-00105
Permit Details
Apply Date:
01/13/2023
Applicant:
Hector Jimenez
Description:
*Revision #1 (SF expansion) started 7/3/2024* Development Plan addressing Minor Changes and Change of Use is being submitted for review. Change of use from Commercial Business use to Residential MF. No Change is square footage.
Permit Reviews
Permit Number - TD-DEV-0123-00105
Permit Status: Issued
Permit Description: *Revision #1 (SF expansion) started 7/3/2024* Development Plan addressing Minor Changes and Change of Use is being submitted for review. Change of use from Commercial Business use to Residential MF. No Change is square footage.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/15/2023 | DEVELOPMENT PACKAGE REVIEW v.2 | 04/13/2023 | REQUIRES RESUBMIT |
| 07/03/2024 | DEVELOPMENT PACKAGE REVIEW v.1 | 07/30/2024 | REQUIRES RESUBMIT |
| 05/11/2023 | DEVELOPMENT PACKAGE REVIEW v.4 | 05/23/2023 | APPROVED |
| 09/27/2024 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 11/20/2024 | APPROVED |
| 01/18/2023 | DEVELOPMENT PACKAGE REVIEW v.1 | 02/24/2023 | REQUIRES RESUBMIT |
| 04/20/2023 | DEVELOPMENT PACKAGE REVIEW v.3 | 05/10/2023 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Issued
Permit Number: TD-DEV-0123-00105
Permite Description: *Revision #1 (SF expansion) started 7/3/2024* Development Plan addressing Minor Changes and Change of Use is being submitted for review. Change of use from Commercial Business use to Residential MF. No Change is square footage.
Total Outstanding Inspections - 8
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/16/2023 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | no activity |
| 10/16/2023 | ENGR - Drainage Structures | N/A | Not Ready | no activity. |
| 10/16/2023 | PDSD Site/Engineering Division - NPPO | N/A | Not Ready | no activity |
| 10/16/2023 | COT - ENGR - Site - Assurance Release | N/A | Not Ready | no activity |
| 10/16/2023 | SITE - Stormwater Setup and Controls | N/A | Not Ready | no activity |
| 10/16/2023 | COT - ENGR - Stormwater | N/A | Not Ready | no activity |
| 10/16/2023 | COT - ENGR - Signage Final | N/A | Not Ready | no activity |
| 06/02/2026 | PDSD Engineering Division Pre-Construction SITE | N/A | Failed | Units’ accessible entrances exceed the allowed slope, there should be a landing with slopes less than 2% in all directions for each unit. 6/2/26 - Site visit to assess progress due to no inspections being called. The ADA pathway called out on the east side has cross slopes greater than the allowable 2%. Trash enclosure is not built to TSM 8-01.9 standards. Driveway aprons and sidewalks are called out in plans but a Right-of-Way permit has not been issued. Pergola between buildings is not on plans, is wobbly, and knocks into the fire riser pipes. At this point, parking lots are untouched, plans call for new paving and striping. |
Completed Inspections
Permit Status: Issued
Permit Number: TD-DEV-0123-00105
Permit Description: *Revision #1 (SF expansion) started 7/3/2024* Development Plan addressing Minor Changes and Change of Use is being submitted for review. Change of use from Commercial Business use to Residential MF. No Change is square footage.
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/23/2026 | Consultation SITE | Passed |