Permit: TC-UTL-1225-00124
Permit Details
Status:
Inspections Complete
Type:
Utilities Permit
Address:
4070 E 29TH ST
Address NEW:
4070 E 29TH ST
Apply Date:
12/18/2025
Applicant:
Sylvette Cuezon
Description:
Install Verizon antennas on existing monopole tower. Install Verizon 50KW Diesel Generator and cabinets on new concrete slab within existing fence enclosure.
Permit Reviews
Permit Number - TC-UTL-1225-00124
Permit Status: Inspections complete
Permit Description: Install Verizon antennas on existing monopole tower. Install Verizon 50KW Diesel Generator and cabinets on new concrete slab within existing fence enclosure.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/19/2025 | UTILITIES REVIEW v.1 | 01/26/2026 | APPROVED |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-UTL-1225-00124
Permite Description: Install Verizon antennas on existing monopole tower. Install Verizon 50KW Diesel Generator and cabinets on new concrete slab within existing fence enclosure.
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/28/2026 | COT - FCON - Fire - Final | N/A | Not Applicable |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-UTL-1225-00124
Permit Description: Install Verizon antennas on existing monopole tower. Install Verizon 50KW Diesel Generator and cabinets on new concrete slab within existing fence enclosure.
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/02/2026 | COT - LCEL - Electrical Underground | Passed | ||
| 04/07/2026 | COT - LCBU - Excavation/Rebar/Zoning | Passed | 4.7.26 Approved Ok to pour |
|
| 04/21/2026 | BULD - Electrical Clearance | Passed | 4/21/26 passed CLEARANCE ECO | |
| 04/21/2026 | COT - LCEL - Electrical Final | Passed | 4/21/26 passed CLEARANCE ECO | |
| 04/28/2026 | COT - LCBU - Building Final | Passed |