Permit: TC-UTL-0626-00088
Permit Details
Apply Date:
07/02/2026
Applicant:
Aaron Flores
Description:
Fee Testing Permit For July 1 Fee Schedule Implementation. Site Utility
Permit Reviews
Permit Number - TC-UTL-0626-00088
Permit Status: Approved
Permit Description: Fee Testing Permit For July 1 Fee Schedule Implementation. Site Utility
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/23/2026 | PRIVATE UTILITY v.1 | N/A | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-UTL-0626-00088
Permit Status: Approved
Permit Description: Fee Testing Permit For July 1 Fee Schedule Implementation. Site Utility
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/22/2026 | • Deferred Items: The following items are not required for initial DP approval but must be submitted under the Utility Permit as deferred submittals prior to final inspections: o Site electrical distribution o Site lighting systems |