Permit: TC-UTL-0623-00068
Permit Details
Apply Date:
06/02/2023
Applicant:
Brad Farkas
Description:
Installation of new 50' monopole, 30'x20'x8' CMU wall, new telco and electrical service
Permit Reviews
Permit Number - TC-UTL-0623-00068
Permit Status: Inspections complete
Permit Description: Installation of new 50' monopole, 30'x20'x8' CMU wall, new telco and electrical service
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/02/2023 | UTILITIES REVIEW v.1 | 07/10/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-UTL-0623-00068
Permit Status: Inspections complete
Permit Description: Installation of new 50' monopole, 30'x20'x8' CMU wall, new telco and electrical service
Total Outstanding Activity Conditions - 6
Date | Name |
---|---|
07/10/2023 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. |
07/10/2023 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
07/10/2023 | The generator shall include a fuel catchment feature designed to contain at least 210 gallons of fuel in the event of a leak. |
07/10/2023 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
07/10/2023 | SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED. |
07/10/2023 | SPECIAL INSPECTION FOR WELDING IS REQUIRED, SUBMIT THE SHOP/FABRICATOR CERTIFICATE ISSUED BY A NATIONALLY KNOWN WELDING SHOP CERTIFIER. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-UTL-0623-00068
Permite Description: Installation of new 50' monopole, 30'x20'x8' CMU wall, new telco and electrical service
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/02/2023 | COT - LCBU - Building Final | N/A | Partial Pass | 8' high equipment perimeter wall is completed to top bond beam. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-UTL-0623-00068
Permit Description: Installation of new 50' monopole, 30'x20'x8' CMU wall, new telco and electrical service
Total Completed Inspections - 6
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/08/2023 | COT - LCEL - Electrical Underground | Passed | 9/8/23: ground ring passed and under ground conduit from and SES to ILC ok to back fill | |
09/22/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | 9/22/23: rebar to plan okay to pour concrete for footing of CMU wall | |
11/22/2023 | COT - LCEL - Grounding/Bonding | Passed | ||
11/22/2023 | BULD - Electrical Clearance | Passed | Approved new service panel (Verizon), ECO Clearance to TEP is required | |
03/13/2024 | COT - LCBU - Building Final | Passed | Approved and completed cell site | |
03/13/2024 | COT - LCEL - Electrical Final | Passed | Approved and completed cell site |