Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Utilities Permit
Address:
190 N SHANNON RD
Address NEW:
190 N SHANNON RD
Apply Date:
04/22/2024
Applicant:
dan wilson
Description:
New 50' Cell-Tower within the existing TEP substation

Permit Reviews

Permit Number - TC-UTL-0424-00014
Permit Status: Complete
Permit Description: New 50' Cell-Tower within the existing TEP substation
Start Date Submittal Complete Date Status  
11/21/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/25/2025 REQUIRES RESUBMIT Review Details
04/25/2024 UTILITIES REVIEW v.1 04/25/2024 REQUIRES RESUBMIT Review Details
05/16/2024 UTILITIES REVIEW v.2 06/18/2024 APPROVED Review Details
12/29/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 01/02/2026 APPROVED Review Details

Conditions

Permit Number - TC-UTL-0424-00014
Permit Status: Complete
Permit Description: New 50' Cell-Tower within the existing TEP substation
Date Description Comments
06/18/2024 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
06/18/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
04/25/2024 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
06/18/2024 SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED.
06/18/2024 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-UTL-0424-00014
Permite Description: New 50' Cell-Tower within the existing TEP substation
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
04/02/2025 COT - LCEL - Grounding/Bonding N/A Partial Pass 4/2/25: grounding per plan for electrical clearance at panel ok to proceed

Completed Inspections

Permit Status: Complete
Permit Number: TC-UTL-0424-00014
Permit Description: New 50' Cell-Tower within the existing TEP substation
Total Completed Inspections - 6
Date Description Inspector Results Comments
04/02/2025 BULD - Electrical Clearance Passed 4/2/25: TEP ECO CLEARANCE FOR 190 N SHANNON RD (T-MOBILE).
04/02/2025 COT - LCEL - Electrical Underground Passed
11/12/2025 COT - LCBU - Excavation/Rebar/Zoning Passed
11/12/2025 COT - LCEL - Electrical Final Passed
11/12/2025 COT - LCBU - Building Final Passed
11/12/2025 COT - LCEL - Grounding/Bonding Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-PH69344A CD'S_V1.PDF DOCUMENTS VIEW
PH69344A AERIAL_V1.PDF DOCUMENTS VIEW
PH69344A IT FORM-RFGS COPY_V1.PDF DOCUMENTS VIEW
PH69344A PIER FOUNDATION CALC'S_V1.PDF DOCUMENTS VIEW