Permit: TC-SOL-1225-01615
Permit Details
Apply Date:
12/19/2025
Applicant:
Inty Ops
Description:
REV. 1: 03/02/2026 Installation of a 4.19 kW (AC) PV System + Battery Storage
Permit Reviews
Permit Number - TC-SOL-1225-01615
Permit Status: Inspections
Permit Description: REV. 1: 03/02/2026
Installation of a 4.19 kW (AC) PV System + Battery Storage
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/27/2026 | RESIDENTIAL SOLAR REVISION v.1 | N/A | REQUIRES RESUBMIT |
| 03/02/2026 | RESIDENTIAL SOLAR REVISION v.2 | N/A | APPROVED |
| 12/22/2025 | RESIDENTIAL SOLAR APP v.1 | 12/22/2025 | APPROVED |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-SOL-1225-01615
Permit Description: REV. 1: 03/02/2026
Installation of a 4.19 kW (AC) PV System + Battery Storage
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/05/2026 | BULD - Electrical Clearance | Passed | 06/05/2026 Clearance TEP GDC/BAT. Verified SolarAPP checklist. |
|
| 06/05/2026 | COT - RSOL - Electrical Final Solar Project | Passed |