Permit: TC-SOL-1124-00758
Permit Details
Apply Date:
11/18/2024
Applicant:
Project Manager
Description:
Installation of a 9.480kw dc system/MPU 225A
Permit Reviews
Permit Number - TC-SOL-1124-00758
Permit Status: Complete
Permit Description: Installation of a 9.480kw dc system/MPU 225A
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/13/2025 | RESIDENTIAL SOLAR REVISION v.1 | 01/13/2025 | APPROVED |
| 11/20/2024 | RESIDENTIAL SOLAR APP v.1 | 11/20/2024 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-SOL-1124-00758
Permite Description: Installation of a 9.480kw dc system/MPU 225A
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/08/2025 | BULD - Electrical Clearance | N/A | Partial Pass | 1/8/25 Approval for TEP INCR, partial pass pending on solar. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-SOL-1124-00758
Permit Description: Installation of a 9.480kw dc system/MPU 225A
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/14/2025 | BULD - Electrical Clearance | Passed | Approved with pics - DGC Clearance to TEP is required for the solar meter | |
| 01/14/2025 | COT - RSOL - Electrical Final Solar Project | Passed |