Permit: TC-SOL-1024-00706
Permit Details
Apply Date:
10/31/2024
Applicant:
Alex Villanueva
Description:
Rev. 2: 08/08/2025 -- Rev. 1: 04/17/2025 -- Solar Panel Installation
Permit Reviews
Permit Number - TC-SOL-1024-00706
Permit Status: Complete
Permit Description: Rev. 2: 08/08/2025 --
Rev. 1: 04/17/2025 --
Solar Panel Installation
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/17/2025 | RESIDENTIAL SOLAR REVISION v.1 | 04/17/2025 | APPROVED |
| 08/12/2025 | RESIDENTIAL SOLAR REVISION v.3 | 08/12/2025 | APPROVED |
| 10/31/2024 | RESIDENTIAL SOLAR APP v.1 | 10/31/2024 | APPROVED |
| 08/08/2025 | RESIDENTIAL SOLAR REVISION v.1 | 08/08/2025 | REQUIRES RESUBMIT |
| 08/12/2025 | RESIDENTIAL SOLAR REVISION v.2 | 08/12/2025 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-SOL-1024-00706
Permite Description: Rev. 2: 08/08/2025 --
Rev. 1: 04/17/2025 --
Solar Panel Installation
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/06/2025 | BULD - Electrical Clearance | N/A | Canceled | 3/5/25 canceled |
| 08/07/2025 | COT - RSOL - Electrical Final Solar Project | N/A | Re-inspection required | 8/7/25 Work not per plan. Submit revision. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-SOL-1024-00706
Permit Description: Rev. 2: 08/08/2025 --
Rev. 1: 04/17/2025 --
Solar Panel Installation
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/12/2025 | BULD - Electrical Clearance | Passed | Approved solar - DGC Clearance to TEP is required for the solar meter | |
| 08/12/2025 | COT - RSOL - Electrical Final Solar Project | Passed |