Permit: TC-SOL-1024-00685
Permit Details
Apply Date:
10/25/2024
Applicant:
Project Manager
Description:
Installation of a 5.530kw dc system/MPU 125A
Permit Reviews
Permit Number - TC-SOL-1024-00685
Permit Status: Complete
Permit Description: Installation of a 5.530kw dc system/MPU 125A
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/25/2024 | RESIDENTIAL SOLAR APP v.1 | 10/25/2024 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-SOL-1024-00685
Permite Description: Installation of a 5.530kw dc system/MPU 125A
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/14/2025 | BULD - Electrical Clearance | N/A | Partial Pass | Partial for the 125A service panel upgrade - INCR Clearance to TEP is required for the cutover Pending solar |
Completed Inspections
Permit Status: Complete
Permit Number: TC-SOL-1024-00685
Permit Description: Installation of a 5.530kw dc system/MPU 125A
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/31/2025 | BULD - Electrical Clearance | Passed | Installed per plans, grounding and bonding per code, CLEARANCE DGC | |
| 01/31/2025 | COT - RSOL - Electrical Final Solar Project | Passed | Installed per plans, grounding and bonding per code, CLEARANCE DGC |