Permit: TC-SOL-0925-01303
Permit Details
Apply Date:
09/25/2025
Applicant:
Marytine Ramos
Description:
Installation of 4.56 kW PV System with 225A MPU
Permit Reviews
Permit Number - TC-SOL-0925-01303
Permit Status: Inspections
Permit Description: Installation of 4.56 kW PV System with 225A MPU
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/25/2025 | RESIDENTIAL SOLAR APP v.1 | 09/25/2025 | APPROVED |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-SOL-0925-01303
Permite Description: Installation of 4.56 kW PV System with 225A MPU
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/30/2025 | BULD - Electrical Clearance | N/A | Partial Pass | 12.30.25 MPU verified per specs, grounding in place at rods, water and gas. Riser secured in 2 spots. Mast is braced and neutrals marked. Deadfront has no extra openings. Label verified. APPROVED FOR INCR TO TEP. partial pending PV |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-SOL-0925-01303
Permit Description: Installation of 4.56 kW PV System with 225A MPU
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/06/2026 | BULD - Electrical Clearance | Passed | 1.6.26 Approved for DGC Clearance to TEP |
|
| 01/06/2026 | COT - RSOL - Electrical Final Solar Project | Passed |