Permit: TC-SOL-0925-01293
Permit Details
Apply Date:
09/23/2025
Applicant:
Marytine Ramos
Description:
Installation of 9.13 kW PV System with SE battery
Permit Reviews
Permit Number - TC-SOL-0925-01293
Permit Status: Inspections
Permit Description: Installation of 9.13 kW PV System with SE battery
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/23/2025 | RESIDENTIAL SOLAR APP v.1 | 09/23/2025 | APPROVED |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-SOL-0925-01293
Permit Description: Installation of 9.13 kW PV System with SE battery
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/21/2025 | BULD - Electrical Clearance | Passed | passed solar final 11/21/25 CLEARANCE DGC/BAT | |
| 11/21/2025 | COT - RSOL - Electrical Final Solar Project | Passed | passed solar final 11/21/25 CLEARANCE DGC/BAT |