Permit: TC-SOL-0925-01192
Permit Details
Apply Date:
09/02/2025
Applicant:
Hailey McGaw
Description:
THIS PROJECT IS COMPRISED OF THE FOLLOWING: · (12) NEW PHOTOVOLTAIC MODULES · (12) NEW DC/AC INVERTER(S) · (01) NEW PHOTOVOLTAIC AC COMBINER PANEL · (01) NEW UTILITY DG METER SOCKET · (01) NEW UTILITY DG DISCONNECT SWITCH · (01) NEW PHOTOVOLTAIC BACK-FEED BREAKER · (18) NEW PHOTOVOLTAIC ROOF MOUNTING HARDWARE WITH INTEGRATED BONDING
Permit Reviews
Permit Number - TC-SOL-0925-01192
Permit Status: Complete
Permit Description: THIS PROJECT IS COMPRISED OF THE FOLLOWING:
· (12) NEW PHOTOVOLTAIC MODULES
· (12) NEW DC/AC INVERTER(S)
· (01) NEW PHOTOVOLTAIC AC COMBINER PANEL
· (01) NEW UTILITY DG METER SOCKET
· (01) NEW UTILITY DG DISCONNECT SWITCH
· (01) NEW PHOTOVOLTAIC BACK-FEED BREAKER
· (18) NEW PHOTOVOLTAIC ROOF MOUNTING HARDWARE WITH INTEGRATED BONDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/02/2025 | RESIDENTIAL SOLAR APP v.1 | 09/02/2025 | APPROVED |
Completed Inspections
Permit Status: Complete
Permit Number: TC-SOL-0925-01192
Permit Description: THIS PROJECT IS COMPRISED OF THE FOLLOWING:
· (12) NEW PHOTOVOLTAIC MODULES
· (12) NEW DC/AC INVERTER(S)
· (01) NEW PHOTOVOLTAIC AC COMBINER PANEL
· (01) NEW UTILITY DG METER SOCKET
· (01) NEW UTILITY DG DISCONNECT SWITCH
· (01) NEW PHOTOVOLTAIC BACK-FEED BREAKER
· (18) NEW PHOTOVOLTAIC ROOF MOUNTING HARDWARE WITH INTEGRATED BONDING
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/02/2025 | BULD - Electrical Clearance | Passed | Approved solar - DGC Clearance to TEP is required for the solar meter | |
| 10/02/2025 | COT - RSOL - Electrical Final Solar Project | Passed |