Permit: TC-SOL-0925-01190
Permit Details
Apply Date:
09/02/2025
Applicant:
Hailey McGaw
Description:
THIS PROJECT IS COMPRISED OF THE FOLLOWING: · (27) NEW PHOTOVOLTAIC MODULES · (27) NEW DC/AC INVERTER(S) · (01) NEW PHOTOVOLTAIC AC COMBINER PANEL · (01) NEW UTILITY DG METER SOCKET · (01) NEW UTILITY DG DISCONNECT SWITCH · (01) NEW MAIN SERVICE UPGRADE · (01) NEW PHOTOVOLTAIC BACK-FEED BREAKER · (46) NEW PHOTOVOLTAIC ROOF MOUNTING HARDWARE WITH INTEGRATED BONDING
Permit Reviews
Permit Number - TC-SOL-0925-01190
Permit Status: Inspections
Permit Description: THIS PROJECT IS COMPRISED OF THE FOLLOWING:
· (27) NEW PHOTOVOLTAIC MODULES
· (27) NEW DC/AC INVERTER(S)
· (01) NEW PHOTOVOLTAIC AC COMBINER PANEL
· (01) NEW UTILITY DG METER SOCKET
· (01) NEW UTILITY DG DISCONNECT SWITCH
· (01) NEW MAIN SERVICE UPGRADE
· (01) NEW PHOTOVOLTAIC BACK-FEED BREAKER
· (46) NEW PHOTOVOLTAIC ROOF MOUNTING HARDWARE WITH INTEGRATED BONDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/02/2025 | RESIDENTIAL SOLAR APP v.1 | 09/02/2025 | APPROVED |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-SOL-0925-01190
Permite Description: THIS PROJECT IS COMPRISED OF THE FOLLOWING:
· (27) NEW PHOTOVOLTAIC MODULES
· (27) NEW DC/AC INVERTER(S)
· (01) NEW PHOTOVOLTAIC AC COMBINER PANEL
· (01) NEW UTILITY DG METER SOCKET
· (01) NEW UTILITY DG DISCONNECT SWITCH
· (01) NEW MAIN SERVICE UPGRADE
· (01) NEW PHOTOVOLTAIC BACK-FEED BREAKER
· (46) NEW PHOTOVOLTAIC ROOF MOUNTING HARDWARE WITH INTEGRATED BONDING
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/29/2025 | BULD - Electrical Clearance | N/A | Canceled | Canceled per contractor. 10/29/2025 |
| 10/29/2025 | COT - RSOL - Electrical Final Solar Project | N/A | Canceled | Canceled per contractor. 10/29/2025 |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-SOL-0925-01190
Permit Description: THIS PROJECT IS COMPRISED OF THE FOLLOWING:
· (27) NEW PHOTOVOLTAIC MODULES
· (27) NEW DC/AC INVERTER(S)
· (01) NEW PHOTOVOLTAIC AC COMBINER PANEL
· (01) NEW UTILITY DG METER SOCKET
· (01) NEW UTILITY DG DISCONNECT SWITCH
· (01) NEW MAIN SERVICE UPGRADE
· (01) NEW PHOTOVOLTAIC BACK-FEED BREAKER
· (46) NEW PHOTOVOLTAIC ROOF MOUNTING HARDWARE WITH INTEGRATED BONDING
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/31/2025 | BULD - Electrical Clearance | Passed | Clearance for TEP DGC. 10/31/2025 | |
| 10/31/2025 | COT - RSOL - Electrical Final Solar Project | Passed |