Permit: TC-SOL-0924-00482
Permit Details
Apply Date:
09/05/2024
Applicant:
Marytine Ramos
Description:
Solarapp - Installation of 8.40kW PV System / ConnectDER
Permit Reviews
Permit Number - TC-SOL-0924-00482
Permit Status: Complete
Permit Description: Solarapp - Installation of 8.40kW PV System / ConnectDER
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/10/2024 | RESIDENTIAL SOLAR APP v.1 | 09/10/2024 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-SOL-0924-00482
Permite Description: Solarapp - Installation of 8.40kW PV System / ConnectDER
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/31/2024 | BULD - Electrical Clearance | N/A | Partial Pass | Partial for the 40A meter adapter - DGL Clearance was called into TEP Pending solar |
Completed Inspections
Permit Status: Complete
Permit Number: TC-SOL-0924-00482
Permit Description: Solarapp - Installation of 8.40kW PV System / ConnectDER
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/12/2024 | BULD - Electrical Clearance | Passed | Solar installed per plans, bonding and labeling proper Clearance DGC 11/12/24 | |
| 11/12/2024 | COT - RSOL - Electrical Final Solar Project | Passed | Solar installed per plans, bonding and labeling proper Clearance DGC 11/12/24 |