Permit: TC-SOL-0826-00469
Permit Details
Apply Date:
08/05/2026
Applicant:
Inty Ops
Description:
Installation of a 11.50 KW (AC) PV System with battery integrated
Permit Reviews
Permit Number - TC-SOL-0826-00469
Permit Status: Inspections
Permit Description: Installation of a 11.50 KW (AC) PV System with battery integrated
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/06/2026 | RESIDENTIAL SOLAR APP v.1 | N/A | APPROVED |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-SOL-0826-00469
Permit Description: Installation of a 11.50 KW (AC) PV System with battery integrated
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/09/2026 | COT - RSOL - Electrical Final Solar Project | Passed | ||
| 09/09/2026 | BULD - Electrical Clearance | Passed | Verbal clearance to TEP DGL. (Tesla backup switch) Final inspection completed same day. Clearances to TEP DGC/DGL/BAT. 9/9/2026 |