Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-SOL-0825-01125
Permit Details
Apply Date:
08/21/2025
Applicant:
Marytine Ramos
Description:
REV. 1: 09/16/2025 -- Installation of 14.62 kW PV System with Batteries
Permit Reviews
Permit Number - TC-SOL-0825-01125
Permit Status: Complete
Permit Description: REV. 1: 09/16/2025 --
Installation of 14.62 kW PV System with Batteries
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/21/2025 | RESIDENTIAL SOLAR APP v.1 | 08/21/2025 | APPROVED |
| 09/16/2025 | RESIDENTIAL SOLAR REVISION v.1 | 09/16/2025 | APPROVED |
Completed Inspections
Permit Status: Complete
Permit Number: TC-SOL-0825-01125
Permit Description: REV. 1: 09/16/2025 --
Installation of 14.62 kW PV System with Batteries
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/24/2025 | BULD - Electrical Clearance | Passed | 9.24.2025 Clearance to TEP DGC/BAT. |
|
| 09/24/2025 | COT - RSOL - Electrical Final Solar Project | Passed |