Permit: TC-SOL-0824-00406
Permit Details
Apply Date:
08/19/2024
Applicant:
Gilberto Sanchez
Description:
Due to the fact that this project is within a regulated floodplain and requires a Floodplain Use Permit (FUP.), we have moved this project into a standard 30 Day Review Time Frame. Please start a new FUP at our permit application web page: https://tdc-online.tucsonaz.gov/#/home NOTE: Documentation of a cost estimate will be required for solar installations. The cost estimate must have a cost breakdown, it must include both the cost of materials and the cost of labor, and it may not be a leasing document. Instructions: 1. Navigate into the current project in the “My Work” tab. Within the permit, navigate to the “Sub-Records” tab and click “Apply” on the Floodplain Use Permit Sub-Record 2. Locations -> Confirm the location is accurate to the project. Click “Next” 3. Type -> Fill in the “Square Feet” and “Valuation” boxes with the project area and a contractor-provided cost estimate (See note above: for new structures, input 0). Click “Next” 4. Contacts -> Confirm contacts and add any additional contacts if applicable. Click “Next” 5. More Info -> This will be filled in by the engineer assigned to your case, Click “Next” 6. Attachments -> Please attach the project plan, supporting documentation for the cost estimate (if applicable), and a drainage/hydrology report (if applicable). Click “Next” 7. Signature -> Read the statement and type your name. Sign your name below (You may Enable Type Signature to have the software sign for you.) Click “Next” 8. Review and Submit -> Review all information to ensure accuracy. Click “Submit” Contact Michael Ortiz at michael.ortiz@tucsonaz.gov if you have any questions about the FUP. APPROVAL ID: SA20240816-9-1080-7097-A 4.920kW DC/ 3.900kW AC PV SYSTEM (12) SEG SOLAR SEG-410-BMD-TB MODULES (12) ENPHASE ENERGY IQ8M-72-2-US
Permit Reviews
Permit Number - TC-SOL-0824-00406
Permit Status: Inspections
Permit Description: Due to the fact that this project is within a regulated floodplain and requires a Floodplain Use Permit (FUP.), we have moved this project into a standard 30 Day Review Time Frame. Please start a new FUP at our permit application web page: https://tdc-online.tucsonaz.gov/#/home NOTE: Documentation of a cost estimate will be required for solar installations. The cost estimate must have a cost breakdown, it must include both the cost of materials and the cost of labor, and it may not be a leasing document. Instructions: 1. Navigate into the current project in the “My Work” tab. Within the permit, navigate to the “Sub-Records” tab and click “Apply” on the Floodplain Use Permit Sub-Record 2. Locations -> Confirm the location is accurate to the project. Click “Next” 3. Type -> Fill in the “Square Feet” and “Valuation” boxes with the project area and a contractor-provided cost estimate (See note above: for new structures, input 0). Click “Next” 4. Contacts -> Confirm contacts and add any additional contacts if applicable. Click “Next” 5. More Info -> This will be filled in by the engineer assigned to your case, Click “Next” 6. Attachments -> Please attach the project plan, supporting documentation for the cost estimate (if applicable), and a drainage/hydrology report (if applicable). Click “Next” 7. Signature -> Read the statement and type your name. Sign your name below (You may Enable Type Signature to have the software sign for you.) Click “Next” 8. Review and Submit -> Review all information to ensure accuracy. Click “Submit” Contact Michael Ortiz at michael.ortiz@tucsonaz.gov if you have any questions about the FUP.
APPROVAL ID: SA20240816-9-1080-7097-A
4.920kW DC/ 3.900kW AC PV SYSTEM
(12) SEG SOLAR SEG-410-BMD-TB MODULES
(12) ENPHASE ENERGY IQ8M-72-2-US
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/20/2024 | RESIDENTIAL SOLAR v.1 | 09/20/2024 | APPROVED |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-SOL-0824-00406
Permit Description: Due to the fact that this project is within a regulated floodplain and requires a Floodplain Use Permit (FUP.), we have moved this project into a standard 30 Day Review Time Frame. Please start a new FUP at our permit application web page: https://tdc-online.tucsonaz.gov/#/home NOTE: Documentation of a cost estimate will be required for solar installations. The cost estimate must have a cost breakdown, it must include both the cost of materials and the cost of labor, and it may not be a leasing document. Instructions: 1. Navigate into the current project in the “My Work” tab. Within the permit, navigate to the “Sub-Records” tab and click “Apply” on the Floodplain Use Permit Sub-Record 2. Locations -> Confirm the location is accurate to the project. Click “Next” 3. Type -> Fill in the “Square Feet” and “Valuation” boxes with the project area and a contractor-provided cost estimate (See note above: for new structures, input 0). Click “Next” 4. Contacts -> Confirm contacts and add any additional contacts if applicable. Click “Next” 5. More Info -> This will be filled in by the engineer assigned to your case, Click “Next” 6. Attachments -> Please attach the project plan, supporting documentation for the cost estimate (if applicable), and a drainage/hydrology report (if applicable). Click “Next” 7. Signature -> Read the statement and type your name. Sign your name below (You may Enable Type Signature to have the software sign for you.) Click “Next” 8. Review and Submit -> Review all information to ensure accuracy. Click “Submit” Contact Michael Ortiz at michael.ortiz@tucsonaz.gov if you have any questions about the FUP.
APPROVAL ID: SA20240816-9-1080-7097-A
4.920kW DC/ 3.900kW AC PV SYSTEM
(12) SEG SOLAR SEG-410-BMD-TB MODULES
(12) ENPHASE ENERGY IQ8M-72-2-US
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/31/2024 | BULD - Electrical Clearance | Passed | Approved - DGC Clearance to TEP is required for the solar meter | |
| 10/31/2024 | COT - RSOL - Electrical Final Solar Project | Passed |