Permit: TC-SOL-0725-01015
Permit Details
Apply Date:
07/29/2025
Applicant:
Marytine Ramos
Description:
Rev. 1: 08/20/2025 -- Installation of 7.79 kW PV System with Battery
Permit Reviews
Permit Number - TC-SOL-0725-01015
Permit Status: Complete
Permit Description: Rev. 1: 08/20/2025 --
Installation of 7.79 kW PV System with Battery
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/20/2025 | RESIDENTIAL SOLAR REVISION v.1 | 08/20/2025 | APPROVED |
| 07/30/2025 | RESIDENTIAL SOLAR APP v.1 | 07/30/2025 | APPROVED |
Completed Inspections
Permit Status: Complete
Permit Number: TC-SOL-0725-01015
Permit Description: Rev. 1: 08/20/2025 --
Installation of 7.79 kW PV System with Battery
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/27/2025 | BULD - Electrical Clearance | Passed | Approved solar and battery - DGC/BAT Clearance to TEP is required for the solar meter | |
| 08/27/2025 | COT - RSOL - Electrical Final Solar Project | Passed |