Permit: TC-SOL-0725-00915
Permit Details
Apply Date:
07/03/2025
Applicant:
Marytine Ramos
Description:
REV 1: 08/22/2025 Installation of 11.07 kW PV System with UBAT-10K1P Battery
Permit Reviews
Permit Number - TC-SOL-0725-00915
Permit Status: Complete
Permit Description: REV 1: 08/22/2025
Installation of 11.07 kW PV System with UBAT-10K1P Battery
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/22/2025 | RESIDENTIAL SOLAR REVISION v.1 | 08/22/2025 | APPROVED |
| 07/03/2025 | RESIDENTIAL SOLAR APP v.1 | 07/03/2025 | APPROVED |
Completed Inspections
Permit Status: Complete
Permit Number: TC-SOL-0725-00915
Permit Description: REV 1: 08/22/2025
Installation of 11.07 kW PV System with UBAT-10K1P Battery
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/04/2025 | BULD - Electrical Clearance | Passed | Approved solar with Battery - DGC/BAT Clearance to TEP is required for the solar meter | |
| 09/04/2025 | COT - RSOL - Electrical Final Solar Project | Passed |