INSTALLATION OF A 10.00 kW PV SYSTEM
Permit Reviews
Permit Number - TC-SOL-0724-00303
Permit Status: Complete
Permit Description: INSTALLATION OF A 10.00 kW PV SYSTEM
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/26/2024 | RESIDENTIAL SOLAR v.2 | 09/24/2024 | APPROVED |
| 07/30/2024 | RESIDENTIAL SOLAR v.1 | 08/01/2024 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-SOL-0724-00303
Permite Description: INSTALLATION OF A 10.00 kW PV SYSTEM
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/25/2024 | BULD - Electrical Clearance | N/A | Not Ready | |
| 09/25/2024 | COT - RSOL - Electrical Final Solar Project | N/A | Re-inspection required | NR - correct #8 wires up to roof j-box, everything else looks good |
Completed Inspections
Permit Status: Complete
Permit Number: TC-SOL-0724-00303
Permit Description: INSTALLATION OF A 10.00 kW PV SYSTEM
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/04/2024 | BULD - Electrical Clearance | Passed | Approved - DGC Clearance to TEP is required for then solar meter | |
| 10/04/2024 | COT - RSOL - Electrical Final Solar Project | Passed |