Permit: TC-SOL-0724-00240
Permit Details
Apply Date:
07/17/2024
Applicant:
Project Manager
Description:
Installation of a 5.135kw dc system/MPU 225A
Permit Reviews
Permit Number - TC-SOL-0724-00240
Permit Status: Complete
Permit Description: Installation of a 5.135kw dc system/MPU 225A
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/17/2024 | RESIDENTIAL SOLAR APP v.1 | 07/17/2024 | APPROVED |
Completed Inspections
Permit Status: Complete
Permit Number: TC-SOL-0724-00240
Permit Description: Installation of a 5.135kw dc system/MPU 225A
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/13/2024 | BULD - Electrical Clearance | Passed | Approved - DGC Clearance to TEP is required for the solar meter | |
| 08/13/2024 | COT - RSOL - Electrical Final Solar Project | Passed | Approved - DGC Clearance to TEP is required for the solar meter |