241 W SANTA PAULA ST
Apply Date:
06/08/2026
Applicant:
TFS Solar
Description:
Roof mount 8.80 kW DC photovoltaic solar system; 20 modules; 13.5 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 2 strings. Service upgrade to NEW 225A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.

Permit Reviews

Permit Number - TC-SOL-0626-00376
Permit Status: Inspections
Permit Description: Roof mount 8.80 kW DC photovoltaic solar system; 20 modules; 13.5 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 2 strings. Service upgrade to NEW 225A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
Start Date Submittal Complete Date Status  
06/09/2026 RESIDENTIAL SOLAR APP v.1 N/A APPROVED Review Details

Completed Inspections

Permit Status: Inspections
Permit Number: TC-SOL-0626-00376
Permit Description: Roof mount 8.80 kW DC photovoltaic solar system; 20 modules; 13.5 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 2 strings. Service upgrade to NEW 225A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
Total Completed Inspections - 2
Date Description Inspector Results Comments
08/25/2026 BULD - Electrical Clearance Passed 08/25/2026
Clearance TEP DGC/BAT. DGL verbal given at 9am for MSA. Approved per SolarAPP+ checklist.
08/25/2026 COT - RSOL - Electrical Final Solar Project Passed 08/25/2026
Clearance TEP DGC/BAT. DGL verbal given at 9am for MSA. Approved per SolarAPP+ checklist.