Permit: TC-SOL-0625-00778
Permit Details
Apply Date:
06/09/2025
Applicant:
TFS Solar
Description:
Roof mount 5.66 kW DC photovoltaic solar system; 13 modules; 27 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 2 strings. 1 battery expansion pack, (no inverter); 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
Permit Reviews
Permit Number - TC-SOL-0625-00778
Permit Status: Complete
Permit Description: Roof mount 5.66 kW DC photovoltaic
solar system; 13 modules; 27 kWh
Storage, 1 Tesla Powerwall-3
battery with integrated PV inverter
with 2 strings. 1 battery expansion
pack, (no inverter); 200A bus with
200A MCB, interconnection via PCS,
Tesla Backup Switch for whole home
backup.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/09/2025 | RESIDENTIAL SOLAR APP v.1 | 06/09/2025 | APPROVED |
Completed Inspections
Permit Status: Complete
Permit Number: TC-SOL-0625-00778
Permit Description: Roof mount 5.66 kW DC photovoltaic
solar system; 13 modules; 27 kWh
Storage, 1 Tesla Powerwall-3
battery with integrated PV inverter
with 2 strings. 1 battery expansion
pack, (no inverter); 200A bus with
200A MCB, interconnection via PCS,
Tesla Backup Switch for whole home
backup.
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/11/2025 | BULD - Electrical Clearance | Passed | Approved solar with PW3 - DGC/BAT Clearance to TEP is required for the solar meter (DGL called in) | |
| 08/11/2025 | COT - RSOL - Electrical Final Solar Project | Passed |