Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Inspections
Type:
Solar
Address:
1501 N DAY RD
Address NEW:
1501 N DAY RD
Apply Date:
05/05/2026
Applicant:
TFS Solar
Description:
Roof mount 10.44 kW DC photovoltaic solar system; 24 modules; 27 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 3 strings. 1 battery expansion pack, (no inverter). 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup. Replace existing 200A meter base.

Permit Reviews

Permit Number - TC-SOL-0526-00315
Permit Status: Inspections
Permit Description: Roof mount 10.44 kW DC photovoltaic solar system; 24 modules; 27 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 3 strings. 1 battery expansion pack, (no inverter). 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup. Replace existing 200A meter base.
Start Date Submittal Complete Date Status  
05/06/2026 RESIDENTIAL SOLAR APP v.1 N/A APPROVED Review Details

Outstanding Inspections

Permit Status: Inspections
Permit Number: TC-SOL-0526-00315
Permite Description: Roof mount 10.44 kW DC photovoltaic solar system; 24 modules; 27 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 3 strings. 1 battery expansion pack, (no inverter). 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup. Replace existing 200A meter base.
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
06/22/2026 BULD - Electrical Clearance N/A Partial Pass

Completed Inspections

Permit Status: Inspections
Permit Number: TC-SOL-0526-00315
Permit Description: Roof mount 10.44 kW DC photovoltaic solar system; 24 modules; 27 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 3 strings. 1 battery expansion pack, (no inverter). 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup. Replace existing 200A meter base.
Total Completed Inspections - 2
Date Description Inspector Results Comments
06/29/2026 BULD - Electrical Clearance Passed DGC/bat approved
06/29/2026 COT - RSOL - Electrical Final Solar Project Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD (SSRS).PDF DOCUMENTS VIEW
CONS-SCHAFER CHRISTOPHER PV STORAGE-DRAWINGS_V1.PDF DOCUMENTS VIEW
SCHAFER CHRISTOPHER PV STORAGE-SAPP APPROVAL-DOCUMENT-SA20260505-9-297-30-A_V1.PDF DOCUMENTS VIEW
SCHAFER CHRISTOPHER PV STORAGE-SPECS APPROVAL-UPLOADS-SA20260505-9-297-30-A_V1.PDF DOCUMENTS VIEW